Question 87 - MB-300 discussion
A company implements Dynamics 365 Finance.
The company wants to utilize Case management to track project issues and risks and associate them to the projects. Project managers will be responsible for managing the new cases.
You need to configure the system.
What should you do?
A.
Create case category security roles named Issue and Risk and assign them to the Project managers duty.
B.
Create case activities for Issue and Risk
C.
Create parent case categories named Issue and Risk
D.
Create case subcategories named Issue and Risk
Your answer: