ExamGecko

CAPM: Certified Associate in Project Management (PMI-100)

Certified Associate in Project Management (PMI-100)
Vendor:

PMI

Certified Associate in Project Management (PMI-100) Exam Questions: 908
Certified Associate in Project Management (PMI-100)   2.372 Learners
Take Practice Tests
Comming soon
PDF | VPLUS

The CAPM (Certified Associate in Project Management) exam is a key certification for professionals aspiring to advance their careers in project management. Our comprehensive resource for CAPM practice tests, shared by individuals who have successfully passed the exam, provides realistic scenarios and invaluable insights to enhance your exam preparation.

Why Use CAPM Practice Test?

  • Real Exam Experience: Our practice test accurately replicates the format and difficulty of the actual CAPM exam, providing you with a realistic preparation experience.

  • Identify Knowledge Gaps: Practicing with these tests helps you identify areas where you need more study, allowing you to focus your efforts effectively.

  • Boost Confidence: Regular practice with exam-like questions builds your confidence and reduces test anxiety.

  • Track Your Progress: Monitor your performance over time to see your improvement and adjust your study plan accordingly.

Key Features of CAPM Practice Test:

  • Up-to-Date Content: Our community ensures that the questions are regularly updated to reflect the latest exam objectives and technology trends.

  • Detailed Explanations: Each question comes with detailed explanations, helping you understand the correct answers and learn from any mistakes.

  • Comprehensive Coverage: The practice test covers all key topics of the CAPM exam, including project management processes, best practices, and terminology.

  • Customizable Practice: Create your own practice sessions based on specific topics or difficulty levels to tailor your study experience to your needs.

Exam number: CAPM

Exam name: Certified Associate in Project Management (CAPM)

Length of test: 3 hours

Exam format: Multiple-choice questions

Exam language: English

Number of questions in the actual exam: 150 questions

Passing score: Determined through psychometric analysis

Use the member-shared CAPM Practice Test to ensure you’re fully prepared for your certification exam. Start practicing today and take a significant step towards achieving your certification goals!

Related questions

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

A.
Expert judgment
A.
Expert judgment
Answers
B.
Forecasting methods
B.
Forecasting methods
Answers
C.
Earned value management
C.
Earned value management
Answers
D.
Analytical techniques
D.
Analytical techniques
Answers
Suggested answer: D
asked 23/09/2024
carlos soto
36 questions

Why is tailoring in a project necessary?

Become a Premium Member for full access
Unlock Premium Member  Unlock Premium Member

When cost variance is negative and schedule variance is positive, the project is:

Become a Premium Member for full access
Unlock Premium Member  Unlock Premium Member

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

A.
Efficient
A.
Efficient
Answers
B.
Effective
B.
Effective
Answers
C.
Push
C.
Push
Answers
D.
Pull
D.
Pull
Answers
Suggested answer: B
asked 23/09/2024
sidra gray
34 questions

A technique used to determine the cause and degree of difference between baseline and actual performance is:

A.
Product analysis.
A.
Product analysis.
Answers
B.
Variance analysis.
B.
Variance analysis.
Answers
C.
Document analysis,
C.
Document analysis,
Answers
D.
Decomposition.
D.
Decomposition.
Answers
Suggested answer: B
asked 23/09/2024
Leandra Felipe
38 questions

During the execution phase of a project a detect is found. The project manager takes responsibility and with the correct documentation, begins the task necessary to repair the defect. What process was applied?

Become a Premium Member for full access
Unlock Premium Member  Unlock Premium Member

A project using the agile/adaptive approach has reached the Project Integration Management phase.

What is the project manager's key responsibility during this phase?

Become a Premium Member for full access
Unlock Premium Member  Unlock Premium Member

A functional manager is delegating a key project to a project team without a project manager. Which communication method will be most effective?

Become a Premium Member for full access
Unlock Premium Member  Unlock Premium Member

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

A.
Work performance data
A.
Work performance data
Answers
B.
Project documents
B.
Project documents
Answers
C.
Scope baseline
C.
Scope baseline
Answers
D.
Requirements documentation
D.
Requirements documentation
Answers
Suggested answer: B
asked 23/09/2024
John Gevers
26 questions

DRAG DROP

Match each tool or technique with its corresponding Project Cost Management process.


Become a Premium Member for full access
Unlock Premium Member  Unlock Premium Member