ExamGecko
Home / PMI / CAPM / Practice Test 1
Ask Question

PMI CAPM Practice Test 1

00:00:00
Show Answer
Report Issue   Restart test

Question 1 / 40

Which document defines how a project is executed, monitored and controlled, and closed?

Strategic plan
Strategic plan
Project charter
Project charter
Project management plan
Project management plan
Service level agreement
Service level agreement
Comment (0)
Suggested answer: C
asked 23/09/2024
Matthew Wunder
43 questions