Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

Organizational process updates
Organizational process updates
Quality metrics
Quality metrics
Change requests
Change requests
Quality control measurements
Quality control measurements
Comment (0)
Suggested answer: B