The process of defining how the project scope will be validated and controlled is known as:

Define Scope.
Define Scope.
Develop Project Management Plan.
Develop Project Management Plan.
Plan Scope Management.
Plan Scope Management.
Plan Quality Management.
Plan Quality Management.
Comment (0)
Suggested answer: C