Question 41

Report Export Collapse

Which input to the Plan Risk Management process provides information on high-level risks?

Project charter
Project charter
Enterprise environmental factors
Enterprise environmental factors
Stakeholder register
Stakeholder register
Organizational process assets
Organizational process assets
Suggested answer: A
asked 23/09/2024
Adetutu Ogunsowo
49 questions

Question 42

Report Export Collapse

Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

Work performance data
Work performance data
Project documents
Project documents
Scope baseline
Scope baseline
Requirements documentation
Requirements documentation
Suggested answer: B
asked 23/09/2024
John Gevers
34 questions

Question 43

Report Export Collapse

Change requests are processed for review and disposition according to which process?

Control Quality
Control Quality
Control Scope
Control Scope
Monitor and Control Project Work
Monitor and Control Project Work
Perform Integrated Change Control
Perform Integrated Change Control
Suggested answer: D
asked 23/09/2024
Taka Masa
38 questions

Question 44

Report Export Collapse

The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

Work performance information.
Work performance information.
Inspections and audits.
Inspections and audits.
Payment systems.
Payment systems.
Procurement performance reviews.
Procurement performance reviews.
Suggested answer: D
asked 23/09/2024
Misael Mosco Jiménez
44 questions

Question 45

Report Export Collapse

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Project Communications Management
Project Communications Management
Project Integration Management
Project Integration Management
Project Risk Management
Project Risk Management
Project Scope Management
Project Scope Management
Suggested answer: B
asked 23/09/2024
Joseph Varghese
44 questions

Question 46

Report Export Collapse

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

Scope baseline
Scope baseline
Organizational process assets
Organizational process assets
Enterprise environmental factors
Enterprise environmental factors
Risk register
Risk register
Suggested answer: C
asked 23/09/2024
Henry Pitcher
37 questions

Question 47

Report Export Collapse

An output of the Develop Project Team process is:

Organizational process assets.
Organizational process assets.
Enterprise environmental factors updates.
Enterprise environmental factors updates.
Project staff assignments.
Project staff assignments.
Organizational charts and position descriptions.
Organizational charts and position descriptions.
Suggested answer: B
asked 23/09/2024
Kehinde Ifarinde
49 questions

Question 48

Report Export Collapse

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Plan Human Resource Management.
Plan Human Resource Management.
Acquire Project Team.
Acquire Project Team.
Manage Project Team.
Manage Project Team.
Develop Project Team.
Develop Project Team.
Suggested answer: B
asked 23/09/2024
Roberto Recine
52 questions

Question 49

Report Export Collapse

Which item is an example of personnel assessment?

Resource calendar
Resource calendar
Tight matrix
Tight matrix
Team-building activity
Team-building activity
Focus group
Focus group
Suggested answer: D
asked 23/09/2024
Leandra Felipe
42 questions

Question 50

Report Export Collapse

The Plan Stakeholder Management process belongs to which Process Group?

Executing
Executing
Initiating
Initiating
Planning
Planning
Monitoring and Controlling
Monitoring and Controlling
Suggested answer: C
asked 23/09/2024
Verónica Crespo
41 questions