Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

A.
Issue log
A.
Issue log
Answers
B.
Change log
B.
Change log
Answers
C.
Expert judgment
C.
Expert judgment
Answers
D.
Change requests
D.
Change requests
Answers
Suggested answer: B

An input to the Plan Stakeholder Management process is:

A.
The project charter.
A.
The project charter.
Answers
B.
The stakeholder analysis.
B.
The stakeholder analysis.
Answers
C.
A communication management plan.
C.
A communication management plan.
Answers
D.
A stakeholder register.
D.
A stakeholder register.
Answers
Suggested answer: D

An input to the Plan Cost Management process is:

A.
Cost estimates.
A.
Cost estimates.
Answers
B.
Resource calendars,
B.
Resource calendars,
Answers
C.
The project charter,
C.
The project charter,
Answers
D.
The risk register.
D.
The risk register.
Answers
Suggested answer: C

A technique used to determine the cause and degree of difference between baseline and actual performance is:

A.
Product analysis.
A.
Product analysis.
Answers
B.
Variance analysis.
B.
Variance analysis.
Answers
C.
Document analysis,
C.
Document analysis,
Answers
D.
Decomposition.
D.
Decomposition.
Answers
Suggested answer: B

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

A.
Develop Project Team.
A.
Develop Project Team.
Answers
B.
Manage Project Team.
B.
Manage Project Team.
Answers
C.
Acquire Project Team.
C.
Acquire Project Team.
Answers
D.
Plan Human Resource Management.
D.
Plan Human Resource Management.
Answers
Suggested answer: D

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

A.
Mandatory
A.
Mandatory
Answers
B.
Discretionary
B.
Discretionary
Answers
C.
Internal
C.
Internal
Answers
D.
External
D.
External
Answers
Suggested answer: A

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

A.
Monitor and Control Project Work
A.
Monitor and Control Project Work
Answers
B.
Perform Quality Assurance
B.
Perform Quality Assurance
Answers
C.
Close Project or Phase
C.
Close Project or Phase
Answers
D.
Control Scope
D.
Control Scope
Answers
Suggested answer: C

An input to the Manage Project Team process is:

A.
Work performance reports.
A.
Work performance reports.
Answers
B.
Change requests.
B.
Change requests.
Answers
C.
Activity resource requirements.
C.
Activity resource requirements.
Answers
D.
Enterprise environmental factors.
D.
Enterprise environmental factors.
Answers
Suggested answer: A

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

A.
Procurement statement of work
A.
Procurement statement of work
Answers
B.
Purchase order
B.
Purchase order
Answers
C.
Source selection criteria
C.
Source selection criteria
Answers
D.
Bidder conference
D.
Bidder conference
Answers
Suggested answer: A

A large portion of a projects budget is typically expended on the processes in which Process Group?

A.
Executing
A.
Executing
Answers
B.
Planning
B.
Planning
Answers
C.
Monitoring and Controlling
C.
Monitoring and Controlling
Answers
D.
Closing
D.
Closing
Answers
Suggested answer: B
Total 908 questions