A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

A.
Efficient
A.
Efficient
Answers
B.
Effective
B.
Effective
Answers
C.
Push
C.
Push
Answers
D.
Pull
D.
Pull
Answers
Suggested answer: B

Scope, schedule, and cost parameters are integrated in the:

A.
Performance measurement baseline.
A.
Performance measurement baseline.
Answers
B.
Analysis of project forecasts,
B.
Analysis of project forecasts,
Answers
C.
Summary of changes approved in a period,
C.
Summary of changes approved in a period,
Answers
D.
Analysis of past performance.
D.
Analysis of past performance.
Answers
Suggested answer: A

A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

A.
Adaptive
A.
Adaptive
Answers
B.
Predictive
B.
Predictive
Answers
C.
Incremental
C.
Incremental
Answers
D.
Iterative
D.
Iterative
Answers
Suggested answer: B

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

A.
0.50
A.
0.50
Answers
B.
0.67
B.
0.67
Answers
C.
1.50
C.
1.50
Answers
D.
2.00
D.
2.00
Answers
Suggested answer: A

Which item is an input to the Define Activities process?

A.
Schedule data
A.
Schedule data
Answers
B.
Activity list
B.
Activity list
Answers
C.
Risk register
C.
Risk register
Answers
D.
Scope baseline
D.
Scope baseline
Answers
Suggested answer: D

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

A.
Interactive communication
A.
Interactive communication
Answers
B.
Claims administration
B.
Claims administration
Answers
C.
Conflict management
C.
Conflict management
Answers
D.
Performance reporting
D.
Performance reporting
Answers
Suggested answer: B

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

A.
Interrelationship digraphs
A.
Interrelationship digraphs
Answers
B.
Tree diagram
B.
Tree diagram
Answers
C.
Affinity diagram
C.
Affinity diagram
Answers
D.
Network diagram
D.
Network diagram
Answers
Suggested answer: B

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

A.
Planning.
A.
Planning.
Answers
B.
Executing,
B.
Executing,
Answers
C.
Monitoring and Controlling.
C.
Monitoring and Controlling.
Answers
D.
Closing.
D.
Closing.
Answers
Suggested answer: C

Organizational theory is a tool used in which Project Human Resource Management process?

A.
Manage Project Team
A.
Manage Project Team
Answers
B.
Acquire Project Team
B.
Acquire Project Team
Answers
C.
Develop Project Team
C.
Develop Project Team
Answers
D.
Plan Human Resource Management
D.
Plan Human Resource Management
Answers
Suggested answer: D

Which tools or techniques are used in the Plan Schedule Management process?

A.
Benchmarking, expert judgment, and analytical techniques
A.
Benchmarking, expert judgment, and analytical techniques
Answers
B.
Statistical sampling, benchmarking, and meetings
B.
Statistical sampling, benchmarking, and meetings
Answers
C.
Negotiations, pre-assignment, and multi-criteria decision analysis
C.
Negotiations, pre-assignment, and multi-criteria decision analysis
Answers
D.
Expert judgment, analytical techniques, and meetings
D.
Expert judgment, analytical techniques, and meetings
Most voted
Answers (1)
Most voted
Suggested answer: D