A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

A.
Projectized
A.
Projectized
Answers
B.
Weak matrix
B.
Weak matrix
Answers
C.
Functional
C.
Functional
Answers
D.
Balanced matrix
D.
Balanced matrix
Answers
Suggested answer: A

A project charter is an output of which Process Group?

A.
Executing
A.
Executing
Answers
B.
Planning
B.
Planning
Answers
C.
Initiating
C.
Initiating
Answers
D.
Closing
D.
Closing
Answers
Suggested answer: C

Which tool or technique is effective in a project in which the deliverable is not a service or result?

A.
Inspection
A.
Inspection
Answers
B.
Variance analysis
B.
Variance analysis
Answers
C.
Decomposition
C.
Decomposition
Answers
D.
Product analysis
D.
Product analysis
Answers
Suggested answer: D

An element of the project scope statement is:

A.
Acceptance criteria.
A.
Acceptance criteria.
Answers
B.
A stakeholder list.
B.
A stakeholder list.
Answers
C.
A summary budget,
C.
A summary budget,
Answers
D.
High-level risks.
D.
High-level risks.
Answers
Suggested answer: A

Which document describes the necessary information to determine if a project is worth the required investment?

A.
Cost baseline
A.
Cost baseline
Answers
B.
Service level agreement
B.
Service level agreement
Answers
C.
Memorandum of understanding
C.
Memorandum of understanding
Answers
D.
Business case
D.
Business case
Answers
Suggested answer: D

Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

A.
Estimate Costs
A.
Estimate Costs
Answers
B.
Control Costs
B.
Control Costs
Answers
C.
Determine Budget
C.
Determine Budget
Answers
D.
Plan Cost Management
D.
Plan Cost Management
Answers
Suggested answer: B

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

A.
Project team
A.
Project team
Answers
B.
Focus group
B.
Focus group
Answers
C.
Change control board
C.
Change control board
Answers
D.
Project stakeholders
D.
Project stakeholders
Answers
Suggested answer: C

Plan Schedule Management is a process in which Knowledge Area?

A.
Project Scope Management
A.
Project Scope Management
Answers
B.
Project Human Resource Management
B.
Project Human Resource Management
Answers
C.
Project Integration Management
C.
Project Integration Management
Answers
D.
Project Time Management
D.
Project Time Management
Answers
Suggested answer: D

An output of the Validate Scope process is:

A.
A requirements traceability matrix.
A.
A requirements traceability matrix.
Answers
B.
The scope management plan.
B.
The scope management plan.
Answers
C.
Work performance reports.
C.
Work performance reports.
Answers
D.
Change requests.
D.
Change requests.
Answers
Suggested answer: D

The Perform Integrated Change Control process occurs in which Process Group?

A.
Initiating
A.
Initiating
Answers
B.
Executing
B.
Executing
Answers
C.
Monitoring and Controlling
C.
Monitoring and Controlling
Answers
D.
Planning
D.
Planning
Answers
Suggested answer: C