Question 61

Report Export Collapse

Which process determines the risks that may affect the project and documents their characteristics?

Control Risks
Control Risks
Plan Risk Management
Plan Risk Management
Plan Risk Responses
Plan Risk Responses
Identify Risks
Identify Risks
Suggested answer: D
asked 23/09/2024
Marcin CieΓ…›lak
49 questions

Question 62

Report Export Collapse

An example of a group decision-ma king technique is:

Nominal group technique.
Nominal group technique.
Majority.
Majority.
Affinity diagram.
Affinity diagram.
Multi-criteria decision analysis.
Multi-criteria decision analysis.
Suggested answer: B
asked 23/09/2024
Maria Gervasi
47 questions

Question 63

Report Export Collapse

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

mitigate
mitigate
accept
accept
transfer
transfer
avoid
avoid
Suggested answer: C
asked 23/09/2024
Christopher Fiotes
40 questions

Question 64

Report Export Collapse

An output of the Plan Quality Management process is:

A process improvement plan,
A process improvement plan,
Quality control measurements.
Quality control measurements.
Work performance information,
Work performance information,
The project management plan.
The project management plan.
Suggested answer: A
asked 23/09/2024
Jeffrey Agnitsch
47 questions

Question 65

Report Export Collapse

A project manager should document the escalation path for unresolved project risks in the:

Change control plan
Change control plan
Stakeholder register
Stakeholder register
Risk log
Risk log
Communications management plan
Communications management plan
Suggested answer: D
asked 23/09/2024
Felix Imafidon
36 questions

Question 66

Report Export Collapse

Which process in Project Time Management includes reserve analysis as a tool or technique?

Estimate Activity Resources
Estimate Activity Resources
Sequence Activities
Sequence Activities
Estimate Activity Durations
Estimate Activity Durations
Develop Schedule
Develop Schedule
Suggested answer: C
asked 23/09/2024
Brad Mateski
45 questions

Question 67

Report Export Collapse

Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?

Enhance
Enhance
Share
Share
Exploit
Exploit
Accept
Accept
Suggested answer: C
asked 23/09/2024
Pablo Hilario
46 questions

Question 68

Report Export Collapse

Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

Expert judgment.
Expert judgment.
Analytical techniques.
Analytical techniques.
Earned value management.
Earned value management.
Group decision-making techniques.
Group decision-making techniques.
Suggested answer: B
asked 23/09/2024
Mykhailo Vavilov
36 questions

Question 69

Report Export Collapse

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Timing
Timing
Methodology
Methodology
Risk categories
Risk categories
Budgeting
Budgeting
Suggested answer: A
asked 23/09/2024
Marcin Piotrowski
43 questions

Question 70

Report Export Collapse

When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

Negative
Negative
Zero
Zero
Positive
Positive
Free
Free
Suggested answer: C