Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

Plan Procurement Management
Plan Procurement Management
Control Procurements
Control Procurements
Collect Requirements
Collect Requirements
Plan Cost Management
Plan Cost Management
Suggested answer: A
asked 23/09/2024
RAHULREDDY BIRADAVOLU
51 questions

Question 82

Report Export Collapse

Which tool or technique is used to manage change requests and the resulting decisions?

Change control tools
Change control tools
Expert judgment
Expert judgment
Delphi technique
Delphi technique
Change log
Change log
Suggested answer: A
asked 23/09/2024
Keenan Bragg
45 questions

Question 83

Report Export Collapse

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

Work packages.
Work packages.
Accepted deliverables.
Accepted deliverables.
The WBS dictionary.
The WBS dictionary.
The scope baseline.
The scope baseline.
Suggested answer: A
asked 23/09/2024
Mellisa Stroman
44 questions

Question 84

Report Export Collapse

In which Knowledge Area is the project charter developed?

Project Cost Management
Project Cost Management
Project Scope Management
Project Scope Management
Project Time Management
Project Time Management
Project Integration Management
Project Integration Management
Suggested answer: D
asked 23/09/2024
JP Pelovello
54 questions

Question 85

Report Export Collapse

The ability to influence cost is greatest during which stages of the project?

Early
Early
Middle
Middle
Late
Late
Completion
Completion
Suggested answer: A
asked 23/09/2024
Avion Bryant
49 questions

Question 86

Report Export Collapse

Which process involves developing an approximation of the monetary resources needed to complete project activities?

Estimate Costs
Estimate Costs
Control Costs
Control Costs
Determine Budget
Determine Budget
Plan Cost Management
Plan Cost Management
Suggested answer: A
asked 23/09/2024
Nghia To Duc
58 questions

Question 87

Report Export Collapse

Which tool or technique is used in the Develop Project Management Plan process?

Pareto diagram
Pareto diagram
Performance reporting
Performance reporting
SWOT analysis
SWOT analysis
Expert judgment
Expert judgment
Suggested answer: D
asked 23/09/2024
Corey Workman
47 questions

Question 88

Report Export Collapse

Lessons learned are created and project resources are released in which Process Group?

Planning
Planning
Executing
Executing
Closing
Closing
Initiating
Initiating
Suggested answer: C
asked 23/09/2024
Rakesh Sonawane
35 questions

Question 89

Report Export Collapse

When should quality planning be performed?

While developing the project charter
While developing the project charter
In parallel with the other planning processes
In parallel with the other planning processes
As part of a detailed risk analysis
As part of a detailed risk analysis
As a separate step from the other planning processes
As a separate step from the other planning processes
Suggested answer: B
asked 23/09/2024
Storage Junk
53 questions

Question 90

Report Export Collapse

A key benefit of the Manage Communications process is that it enables:

The best use of communication methods.
The best use of communication methods.
An efficient and effective communication flow.
An efficient and effective communication flow.
Project costs to be reduced.
Project costs to be reduced.
The best use of communication technology.
The best use of communication technology.
Suggested answer: B
asked 23/09/2024
George Sanchez
44 questions
Total 908 questions
Go to page: of 91