A regression line is used to estimate:

A.
Whether or not a process is stable or has predictable performance.
A.
Whether or not a process is stable or has predictable performance.
Answers
B.
How a change to the independent variable influences the value of the dependent variable.
B.
How a change to the independent variable influences the value of the dependent variable.
Answers
C.
The upper and lower specification limits on a control chart.
C.
The upper and lower specification limits on a control chart.
Answers
D.
The central tendency, dispersion, and shape of a statistical distribution.
D.
The central tendency, dispersion, and shape of a statistical distribution.
Answers
Suggested answer: B

An input to Conduct Procurements is:

A.
Independent estimates.
A.
Independent estimates.
Answers
B.
Selected sellers.
B.
Selected sellers.
Answers
C.
Seller proposals.
C.
Seller proposals.
Answers
D.
Resource calendars.
D.
Resource calendars.
Answers
Suggested answer: C

What are the Project Procurement Management processes?

A.
Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
A.
Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
Answers
B.
Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
B.
Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
Answers
C.
Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
C.
Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
Answers
D.
Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements
D.
Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements
Answers
Suggested answer: C

Which tool or technique is used to develop the human resource management plan?

A.
Ground rules
A.
Ground rules
Answers
B.
Expert judgment
B.
Expert judgment
Answers
C.
Team-building activities
C.
Team-building activities
Answers
D.
Interpersonal skills
D.
Interpersonal skills
Answers
Suggested answer: B

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

A.
Only once, at the beginning
A.
Only once, at the beginning
Answers
B.
At the beginning and the end
B.
At the beginning and the end
Answers
C.
Once during each phase
C.
Once during each phase
Answers
D.
Repeatedly
D.
Repeatedly
Answers
Suggested answer: D

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

A.
A risk urgency assessment.
A.
A risk urgency assessment.
Answers
B.
The scope baseline.
B.
The scope baseline.
Answers
C.
Work performance information.
C.
Work performance information.
Answers
D.
Procurement audits.
D.
Procurement audits.
Answers
Suggested answer: C

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

A.
Requirements documentation
A.
Requirements documentation
Answers
B.
Requirements traceability matrix
B.
Requirements traceability matrix
Answers
C.
Project management plan updates
C.
Project management plan updates
Answers
D.
Project documents updates
D.
Project documents updates
Answers
Suggested answer: B

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

A.
Cost management plan.
A.
Cost management plan.
Answers
B.
Work performance information.
B.
Work performance information.
Answers
C.
Quality management plan.
C.
Quality management plan.
Answers
D.
Work breakdown structure.
D.
Work breakdown structure.
Answers
Suggested answer: A

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

A.
External
A.
External
Answers
B.
Internal
B.
Internal
Answers
C.
Mandatory
C.
Mandatory
Answers
D.
Discretionary
D.
Discretionary
Answers
Suggested answer: D

Sensitivity analysis is typically displayed as a/an:

A.
Decision tree diagram.
A.
Decision tree diagram.
Answers
B.
Tornado diagram.
B.
Tornado diagram.
Answers
C.
Pareto diagram.
C.
Pareto diagram.
Answers
D.
Ishikawa diagram.
D.
Ishikawa diagram.
Answers
Suggested answer: B