ExamGecko
Home / PMI / CAPM / List of questions
Ask Question

PMI CAPM Practice Test - Questions Answers, Page 11

Add to Whishlist

List of questions

Question 101

Report Export Collapse

A regression line is used to estimate:

Whether or not a process is stable or has predictable performance.
Whether or not a process is stable or has predictable performance.
How a change to the independent variable influences the value of the dependent variable.
How a change to the independent variable influences the value of the dependent variable.
The upper and lower specification limits on a control chart.
The upper and lower specification limits on a control chart.
The central tendency, dispersion, and shape of a statistical distribution.
The central tendency, dispersion, and shape of a statistical distribution.
Suggested answer: B
asked 23/09/2024
Jesserey Joseph
43 questions

Question 102

Report Export Collapse

An input to Conduct Procurements is:

Independent estimates.
Independent estimates.
Selected sellers.
Selected sellers.
Seller proposals.
Seller proposals.
Resource calendars.
Resource calendars.
Suggested answer: C
asked 23/09/2024
Adam Bednar
44 questions

Question 103

Report Export Collapse

What are the Project Procurement Management processes?

Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements
Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements
Suggested answer: C
asked 23/09/2024
Elena Albu
45 questions

Question 104

Report Export Collapse

Which tool or technique is used to develop the human resource management plan?

Ground rules
Ground rules
Expert judgment
Expert judgment
Team-building activities
Team-building activities
Interpersonal skills
Interpersonal skills
Suggested answer: B
asked 23/09/2024
Gerrit Struik
59 questions

Question 105

Report Export Collapse

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Only once, at the beginning
Only once, at the beginning
At the beginning and the end
At the beginning and the end
Once during each phase
Once during each phase
Repeatedly
Repeatedly
Suggested answer: D
asked 23/09/2024
Angad Singh
40 questions

Question 106

Report Export Collapse

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

A risk urgency assessment.
A risk urgency assessment.
The scope baseline.
The scope baseline.
Work performance information.
Work performance information.
Procurement audits.
Procurement audits.
Suggested answer: C
asked 23/09/2024
Peter Sundstrom
38 questions

Question 107

Report Export Collapse

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

Requirements documentation
Requirements documentation
Requirements traceability matrix
Requirements traceability matrix
Project management plan updates
Project management plan updates
Project documents updates
Project documents updates
Suggested answer: B
asked 23/09/2024
Vageesh Shanmukha
52 questions

Question 108

Report Export Collapse

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

Cost management plan.
Cost management plan.
Work performance information.
Work performance information.
Quality management plan.
Quality management plan.
Work breakdown structure.
Work breakdown structure.
Suggested answer: A
asked 23/09/2024
Hristo Slaveev
33 questions

Question 109

Report Export Collapse

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

External
External
Internal
Internal
Mandatory
Mandatory
Discretionary
Discretionary
Suggested answer: D
asked 23/09/2024
GULNUR FICICILAR
36 questions

Question 110

Report Export Collapse

Sensitivity analysis is typically displayed as a/an:

Decision tree diagram.
Decision tree diagram.
Tornado diagram.
Tornado diagram.
Pareto diagram.
Pareto diagram.
Ishikawa diagram.
Ishikawa diagram.
Suggested answer: B
asked 23/09/2024
Anthony Wilson
44 questions
Total 908 questions
Go to page: of 91