ExamGecko
Home / PMI / CAPM / List of questions
Ask Question

PMI CAPM Practice Test - Questions Answers, Page 13

Add to Whishlist

List of questions

Question 121

Report Export Collapse

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

Organizational process updates
Organizational process updates
Quality metrics
Quality metrics
Change requests
Change requests
Quality control measurements
Quality control measurements
Suggested answer: B
asked 23/09/2024
DIEGO MORENO
41 questions

Question 122

Report Export Collapse

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

Urgent information need
Urgent information need
Sensitivity of information
Sensitivity of information
Project environment
Project environment
Ease of use
Ease of use
Suggested answer: C
asked 23/09/2024
Mashudu Abraham
40 questions

Question 123

Report Export Collapse

The number of potential communication channels for a project with 5 stakeholders is:

10.
10.
12.
12.
20.
20.
24.
24.
Suggested answer: A
asked 23/09/2024
Ramesh K
50 questions

Question 124

Report Export Collapse

The process of prioritizing risks for further analysis or action is known as:

Plan Risk Management.
Plan Risk Management.
Plan Risk Responses.
Plan Risk Responses.
Perform Qualitative Risk Analysis.
Perform Qualitative Risk Analysis.
Perform Quantitative Risk Analysis.
Perform Quantitative Risk Analysis.
Suggested answer: C
asked 23/09/2024
Bipindra Shrestha
45 questions

Question 125

Report Export Collapse

Which tool or technique is used in validating the scope of a project?

Facilitated workshops
Facilitated workshops
Interviews
Interviews
Inspection
Inspection
Meetings
Meetings
Suggested answer: C
asked 23/09/2024
Sunila Chugh
42 questions

Question 126

Report Export Collapse

An input to Close Project or Phase is:

Accepted deliverables,
Accepted deliverables,
Final products or services,
Final products or services,
Document updates,
Document updates,
Work performance information.
Work performance information.
Suggested answer: A
asked 23/09/2024
Reydel Tabares Castro
52 questions

Question 127

Report Export Collapse

An output of the Direct and Manage Project Work process is:

Deliverables.
Deliverables.
Activity lists.
Activity lists.
A work breakdown structure.
A work breakdown structure.
A scope statement.
A scope statement.
Suggested answer: A
asked 23/09/2024
Heidar Heidari nia
41 questions

Question 128

Report Export Collapse

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

Customers.
Customers.
Business partners.
Business partners.
Sellers.
Sellers.
Functional managers.
Functional managers.
Suggested answer: B
asked 23/09/2024
Steven Moran
38 questions

Question 129

Report Export Collapse

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

Develop Schedule
Develop Schedule
Create VVBS
Create VVBS
Estimate Activity Resources
Estimate Activity Resources
Define Scope
Define Scope
Suggested answer: B
asked 23/09/2024
Jose Manuel GONZALEZ BALSEIRO
42 questions

Question 130

Report Export Collapse

In a project, total float measures the:

Ability to shuffle schedule activities to lessen the duration of the project.
Ability to shuffle schedule activities to lessen the duration of the project.
Amount of time an activity can be extended or delayed without altering the project finish date.
Amount of time an activity can be extended or delayed without altering the project finish date.
Cost expended to restore order to the project schedule after crashing the schedule.
Cost expended to restore order to the project schedule after crashing the schedule.
Estimate of the total resources needed for the project after performing a forward pass.
Estimate of the total resources needed for the project after performing a forward pass.
Suggested answer: B
asked 23/09/2024
Dean Pillay
53 questions
Total 908 questions
Go to page: of 91