ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 14

Question list
Search
Search

Which Knowledge Areas include processes from the Closing Process Group?

A.
Project Quality Management and Project Time Management
A.
Project Quality Management and Project Time Management
Answers
B.
Project Scope Management and Project Risk Management
B.
Project Scope Management and Project Risk Management
Answers
C.
Project Stakeholder Management and Project Cost Management
C.
Project Stakeholder Management and Project Cost Management
Answers
D.
Project Integration Management and Project Procurement Management
D.
Project Integration Management and Project Procurement Management
Answers
Suggested answer: D

Stakeholder satisfaction should be managed as a key project:

A.
Benefit
A.
Benefit
Answers
B.
Initiative
B.
Initiative
Answers
C.
Objective
C.
Objective
Answers
D.
Process
D.
Process
Answers
Suggested answer: C

Which cost is associated with nonconformance?

A.
Liabilities
A.
Liabilities
Answers
B.
Inspections
B.
Inspections
Answers
C.
Training
C.
Training
Answers
D.
Equipment
D.
Equipment
Answers
Suggested answer: A

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

A.
Historical relationships
A.
Historical relationships
Answers
B.
Dependency determination
B.
Dependency determination
Answers
C.
Bottom-up estimating
C.
Bottom-up estimating
Answers
D.
Rolling wave planning
D.
Rolling wave planning
Answers
Suggested answer: D

An output of the Create WBS process is:

A.
Scope baseline.
A.
Scope baseline.
Answers
B.
Change requests.
B.
Change requests.
Answers
C.
Accepted deliverables.
C.
Accepted deliverables.
Answers
D.
Variance analysis.
D.
Variance analysis.
Answers
Suggested answer: A

A tool or technique used in the Control Procurements process is:

A.
Expert judgment.
A.
Expert judgment.
Answers
B.
Performance reporting.
B.
Performance reporting.
Answers
C.
Bidder conferences.
C.
Bidder conferences.
Answers
D.
Reserve analysis.
D.
Reserve analysis.
Answers
Suggested answer: B

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

A.
Perform Quality Assurance
A.
Perform Quality Assurance
Answers
B.
Direct and Manage Project Work
B.
Direct and Manage Project Work
Answers
C.
Monitor and Control Project Work
C.
Monitor and Control Project Work
Answers
D.
Perform Integrated Change Control
D.
Perform Integrated Change Control
Answers
Suggested answer: D

Which tool or technique is used in the Estimate Costs process?

A.
Acquisition
A.
Acquisition
Answers
B.
Earned value management
B.
Earned value management
Answers
C.
Vendor bid analysis
C.
Vendor bid analysis
Answers
D.
Forecasting
D.
Forecasting
Answers
Suggested answer: C

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

A.
Supportive
A.
Supportive
Answers
B.
Directive
B.
Directive
Answers
C.
Controlling
C.
Controlling
Answers
D.
Instructive
D.
Instructive
Answers
Suggested answer: A

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

A.
Project document updates
A.
Project document updates
Answers
B.
Activity list
B.
Activity list
Answers
C.
Activity attributes
C.
Activity attributes
Answers
D.
Project calendars
D.
Project calendars
Answers
Suggested answer: C
Total 908 questions
Go to page: of 91