Which Knowledge Areas include processes from the Closing Process Group?

Project Quality Management and Project Time Management
Project Quality Management and Project Time Management
Project Scope Management and Project Risk Management
Project Scope Management and Project Risk Management
Project Stakeholder Management and Project Cost Management
Project Stakeholder Management and Project Cost Management
Project Integration Management and Project Procurement Management
Project Integration Management and Project Procurement Management
Suggested answer: D
asked 23/09/2024
OLUWAGBENRO AFUWAPE
45 questions

Question 132

Report Export Collapse

Stakeholder satisfaction should be managed as a key project:

Benefit
Benefit
Initiative
Initiative
Objective
Objective
Process
Process
Suggested answer: C
asked 23/09/2024
Matthew Wunder
44 questions

Question 133

Report Export Collapse

Which cost is associated with nonconformance?

Liabilities
Liabilities
Inspections
Inspections
Training
Training
Equipment
Equipment
Suggested answer: A
asked 23/09/2024
Martynas Abrutis
43 questions

Question 134

Report Export Collapse

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

Historical relationships
Historical relationships
Dependency determination
Dependency determination
Bottom-up estimating
Bottom-up estimating
Rolling wave planning
Rolling wave planning
Suggested answer: D
asked 23/09/2024
Jesus Vargas
59 questions

Question 135

Report Export Collapse

An output of the Create WBS process is:

Scope baseline.
Scope baseline.
Change requests.
Change requests.
Accepted deliverables.
Accepted deliverables.
Variance analysis.
Variance analysis.
Suggested answer: A
asked 23/09/2024
henri victor BOGMIS
46 questions

Question 136

Report Export Collapse

A tool or technique used in the Control Procurements process is:

Expert judgment.
Expert judgment.
Performance reporting.
Performance reporting.
Bidder conferences.
Bidder conferences.
Reserve analysis.
Reserve analysis.
Suggested answer: B
asked 23/09/2024
Mohammedsaleh Ibrahim
44 questions

Question 137

Report Export Collapse

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Perform Quality Assurance
Perform Quality Assurance
Direct and Manage Project Work
Direct and Manage Project Work
Monitor and Control Project Work
Monitor and Control Project Work
Perform Integrated Change Control
Perform Integrated Change Control
Suggested answer: D
asked 23/09/2024
Ravi Kundu
33 questions

Question 138

Report Export Collapse

Which tool or technique is used in the Estimate Costs process?

Acquisition
Acquisition
Earned value management
Earned value management
Vendor bid analysis
Vendor bid analysis
Forecasting
Forecasting
Suggested answer: C
asked 23/09/2024
Mr Fraser Watson
40 questions

Question 139

Report Export Collapse

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

Supportive
Supportive
Directive
Directive
Controlling
Controlling
Instructive
Instructive
Suggested answer: A
asked 23/09/2024
Marcelo Tamaki
43 questions

Question 140

Report Export Collapse

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

Project document updates
Project document updates
Activity list
Activity list
Activity attributes
Activity attributes
Project calendars
Project calendars
Suggested answer: C