PMI CAPM Practice Test - Questions Answers, Page 15
List of questions
Question 141
An input to the Identify Stakeholders process is:
Question 142
Identify Risks is part of which Process Group?
Question 143
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?
Question 144
Which tool or technique is used in the Perform Integrated Change Control process?
Question 145
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
Question 146
Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?
Question 147
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
Question 148
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
Question 149
Which Process Group and Knowledge Area include the Sequence Activities process?
Question 150
In the Plan Stakeholder Management process, expert judgment is used to:
Topic 2, Volume B
Question