ExamGecko
Home / PMI / CAPM / List of questions
Ask Question

PMI CAPM Practice Test - Questions Answers, Page 15

Add to Whishlist

List of questions

Question 141

Report Export Collapse

An input to the Identify Stakeholders process is:

The project management plan.
The project management plan.
The stakeholder register.
The stakeholder register.
Procurement documents.
Procurement documents.
Stakeholder analysis.
Stakeholder analysis.
Suggested answer: C
asked 23/09/2024
Steven Owens
39 questions

Question 142

Report Export Collapse

Identify Risks is part of which Process Group?

Planning
Planning
Executing
Executing
Closing
Closing
Initiating
Initiating
Suggested answer: A
asked 23/09/2024
Vincent Scotti
38 questions

Question 143

Report Export Collapse

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

Force/direct
Force/direct
Withdraw/avoid
Withdraw/avoid
Compromise/reconcile
Compromise/reconcile
Collaborate/problem solve
Collaborate/problem solve
Suggested answer: C
asked 23/09/2024
Bob Tole
53 questions

Question 144

Report Export Collapse

Which tool or technique is used in the Perform Integrated Change Control process?

Decomposition
Decomposition
Modeling techniques
Modeling techniques
Resource optimization
Resource optimization
Meetings
Meetings
Suggested answer: D
asked 23/09/2024
Euwing Mendoza
50 questions

Question 145

Report Export Collapse

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

Start-to-start (SS).
Start-to-start (SS).
Start-to-finish (SF).
Start-to-finish (SF).
Finish-to-start (FS).
Finish-to-start (FS).
Finish-to-finish (FF).
Finish-to-finish (FF).
Suggested answer: C
asked 23/09/2024
Nora Daniels
42 questions

Question 146

Report Export Collapse

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Cost Plus Incentive Fee (CPIF)
Cost Plus Incentive Fee (CPIF)
Fixed Price Incentive Fee (FPIF)
Fixed Price Incentive Fee (FPIF)
Cost Pius Award Re (CPAF)
Cost Pius Award Re (CPAF)
Time and Material (T&M)
Time and Material (T&M)
Suggested answer: B
asked 23/09/2024
Sushil Karki
48 questions

Question 147

Report Export Collapse

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

$50
$50
$100
$100
$125
$125
$175
$175
Suggested answer: C
asked 23/09/2024
Jay Fletcher
54 questions

Question 148

Report Export Collapse

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Project management plan.
Project management plan.
Project charter.
Project charter.
Work breakdown structure.
Work breakdown structure.
Stakeholder register.
Stakeholder register.
Suggested answer: B
asked 23/09/2024
Sullivan Dabireau
45 questions

Question 149

Report Export Collapse

Which Process Group and Knowledge Area include the Sequence Activities process?

Executing Process Group and Project Time Management
Executing Process Group and Project Time Management
Executing Process Group and Project Cost Management
Executing Process Group and Project Cost Management
Planning Process Group and Project Time Management
Planning Process Group and Project Time Management
Planning Process Group and Project Cost Management
Planning Process Group and Project Cost Management
Suggested answer: C
asked 23/09/2024
Morten Sivertsen
33 questions

Question 150

Report Export Collapse

In the Plan Stakeholder Management process, expert judgment is used to:

Provide information needed to plan appropriate ways to engage project stakeholders.
Provide information needed to plan appropriate ways to engage project stakeholders.
Ensure comprehensive identification and listing of new stakeholders.
Ensure comprehensive identification and listing of new stakeholders.
Analyze the information needed to develop the project scope statement.
Analyze the information needed to develop the project scope statement.
Decide the level of engagement of the stakeholders at each required stage.
Decide the level of engagement of the stakeholders at each required stage.
Suggested answer: D
Explanation:

Topic 2, Volume B

asked 23/09/2024
Saeed Awwad
51 questions
Total 908 questions
Go to page: of 91