ExamGecko
Home Home / PMI / CAPM

PMI CAPM Practice Test - Questions Answers, Page 15

Question list
Search
Search

An input to the Identify Stakeholders process is:

A.
The project management plan.
A.
The project management plan.
Answers
B.
The stakeholder register.
B.
The stakeholder register.
Answers
C.
Procurement documents.
C.
Procurement documents.
Answers
D.
Stakeholder analysis.
D.
Stakeholder analysis.
Answers
Suggested answer: C

Identify Risks is part of which Process Group?

A.
Planning
A.
Planning
Answers
B.
Executing
B.
Executing
Answers
C.
Closing
C.
Closing
Answers
D.
Initiating
D.
Initiating
Answers
Suggested answer: A

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

A.
Force/direct
A.
Force/direct
Answers
B.
Withdraw/avoid
B.
Withdraw/avoid
Answers
C.
Compromise/reconcile
C.
Compromise/reconcile
Answers
D.
Collaborate/problem solve
D.
Collaborate/problem solve
Answers
Suggested answer: C

Which tool or technique is used in the Perform Integrated Change Control process?

A.
Decomposition
A.
Decomposition
Answers
B.
Modeling techniques
B.
Modeling techniques
Answers
C.
Resource optimization
C.
Resource optimization
Answers
D.
Meetings
D.
Meetings
Answers
Suggested answer: D

A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

A.
Start-to-start (SS).
A.
Start-to-start (SS).
Answers
B.
Start-to-finish (SF).
B.
Start-to-finish (SF).
Answers
C.
Finish-to-start (FS).
C.
Finish-to-start (FS).
Answers
D.
Finish-to-finish (FF).
D.
Finish-to-finish (FF).
Answers
Suggested answer: C

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

A.
Cost Plus Incentive Fee (CPIF)
A.
Cost Plus Incentive Fee (CPIF)
Answers
B.
Fixed Price Incentive Fee (FPIF)
B.
Fixed Price Incentive Fee (FPIF)
Answers
C.
Cost Pius Award Re (CPAF)
C.
Cost Pius Award Re (CPAF)
Answers
D.
Time and Material (T&M)
D.
Time and Material (T&M)
Answers
Suggested answer: B

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

A.
$50
A.
$50
Answers
B.
$100
B.
$100
Answers
C.
$125
C.
$125
Answers
D.
$175
D.
$175
Answers
Suggested answer: C

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

A.
Project management plan.
A.
Project management plan.
Answers
B.
Project charter.
B.
Project charter.
Answers
C.
Work breakdown structure.
C.
Work breakdown structure.
Answers
D.
Stakeholder register.
D.
Stakeholder register.
Answers
Suggested answer: B

Which Process Group and Knowledge Area include the Sequence Activities process?

A.
Executing Process Group and Project Time Management
A.
Executing Process Group and Project Time Management
Answers
B.
Executing Process Group and Project Cost Management
B.
Executing Process Group and Project Cost Management
Answers
C.
Planning Process Group and Project Time Management
C.
Planning Process Group and Project Time Management
Answers
D.
Planning Process Group and Project Cost Management
D.
Planning Process Group and Project Cost Management
Answers
Suggested answer: C

In the Plan Stakeholder Management process, expert judgment is used to:

A.
Provide information needed to plan appropriate ways to engage project stakeholders.
A.
Provide information needed to plan appropriate ways to engage project stakeholders.
Answers
B.
Ensure comprehensive identification and listing of new stakeholders.
B.
Ensure comprehensive identification and listing of new stakeholders.
Answers
C.
Analyze the information needed to develop the project scope statement.
C.
Analyze the information needed to develop the project scope statement.
Answers
D.
Decide the level of engagement of the stakeholders at each required stage.
D.
Decide the level of engagement of the stakeholders at each required stage.
Answers
Suggested answer: D

Explanation:

Topic 2, Volume B

Total 908 questions
Go to page: of 91