The CompTIA Project+ (PK0-005) exam is a crucial certification for anyone aiming to advance their career in project management. Our topic is your ultimate resource for PK0-005 practice test shared by individuals who have successfully passed the exam. These practice tests provide real-world scenarios and invaluable insights to help you ace your preparation.
Why Use PK0-005 Practice Test?
-
Real Exam Experience: Our practice test accurately replicates the format and difficulty of the actual CompTIA PK0-005 exam, providing you with a realistic preparation experience.
-
Identify Knowledge Gaps: Practicing with these tests helps you identify areas where you need more study, allowing you to focus your efforts effectively.
-
Boost Confidence: Regular practice with exam-like questions builds your confidence and reduces test anxiety.
-
Track Your Progress: Monitor your performance over time to see your improvement and adjust your study plan accordingly.
Key Features of PK0-005 Practice Test:
-
Up-to-Date Content: Our community ensures that the questions are regularly updated to reflect the latest exam objectives and technology trends.
-
Detailed Explanations: Each question comes with detailed explanations, helping you understand the correct answers and learn from any mistakes.
-
Comprehensive Coverage: The practice test covers all key topics of the CompTIA PK0-005 exam, including project management concepts, tools, and techniques.
-
Customizable Practice: Create your own practice sessions based on specific topics or difficulty levels to tailor your study experience to your needs.
Exam Number: PK0-005
Exam Name: CompTIA Project+
Length of test: 90 mins
Exam Format: Multiple-choice, Drag and Drop, and HOTSPOT questions.
Exam Language: English
Number of questions in the actual exam: Maximum of 90 questions
Passing Score: 710/900
Use the shared CompTIA PK0-005 Practice Test to ensure you’re fully prepared for your certification exam. Start practicing today and take a significant step towards achieving your certification goals!
Related questions
During a gate review meeting, the deliverable was rejected by the customer.
INSTRUCTIONS
Review the dashboard.
• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
• Part 2: Select the proper document(s) to be updated.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.
Part 1:
Part 2:
Explanation:
Part 1:
Change Control Process:
Consult the RACI matrix.
Define new requirements and record changes.
Assess the schedule, risk, and cost.
Perform a demonstration.
Obtain a sign off.
Update and test the deliverable.
Make an announcement on the company portal.
The change control process is a sequence of steps that helps to manage and document any changes or modifications to a project scope, schedule, cost, quality, or resources. The change control process typically involves the following steps:
Consult the RACI matrix. A RACI matrix is a tool that defines and clarifies the roles and responsibilities of each team member for each task or activity in a project. RACI stands for responsible, accountable, consulted, and informed. Consulting the RACI matrix can help to identify who needs to be involved or informed about the change request and how to communicate with them.
Define new requirements and record changes. The new requirements and changes are the details of what needs to be modified or added to the project deliverables or objectives based on the customer feedback or request. Defining and recording the new requirements and changes can help to communicate and justify the need and rationale for the change and its implications on the project scope and quality.
Assess the schedule, risk, and cost. The schedule, risk, and cost are the aspects of the project that may be affected by the change request. Assessing the schedule, risk, and cost can help to determine the impact and feasibility of the change and identify any possible alternatives or corrective actions to minimize or avoid its negative effects.
Perform a demonstration. A demonstration is a presentation or show of how the modified or updated deliverable works or meets the customer expectations or requirements. Performing a demonstration can help to validate and verify that the change request has been implemented correctly and effectively and to obtain feedback or approval from the customer or stakeholders.
Obtain a sign off. A sign off is a formal acceptance and approval of the change request and its deliverables from the customer or stakeholders. Obtaining a sign off can help to confirm that the change request has been completed successfully and satisfactorily and to close the change control process.
Update and test the deliverable. The deliverable is the product or service that is produced or provided by the project. Updating and testing the deliverable can help to ensure that it meets the quality standards and criteria and that it works as expected after implementing the change request.
Make an announcement on the company portal. The company portal is a platform or channel that allows internal communication and collaboration among employees within an organization. Making an announcement on the company portal can help to inform and update other team members or departments about the change request and its outcomes and to share any lessons learned or best practices from the change control process.
Part2:
Risk register: A risk register is a document that identifies, analyzes, and records the potential risks or uncertainties that may affect a project. Updating the risk register can help to capture any new or modified risks that may arise from the change request and to plan and implement appropriate risk responses.
Schedule: A schedule is a document that shows the planned start and end dates, durations, dependencies, and progress of each task or activity in a project. Updating the schedule can help to reflect any changes or adjustments to the project timeline or milestones that may result from the change request and to monitor and control the project performance and delivery.
Statement of work: A statement of work (SOW) is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. Updating the SOW can help to document any changes or additions to the project scope or deliverables that may be requested or agreed upon by the customer or stakeholders and to ensure alignment and agreement on what needs to be done and how it will be done.
Change log: A change log is a document that tracks and records any changes or modifications that are made to the project scope, schedule, cost, quality, or resources during a project. Updating the change log can help to document the change request, approval, implementation, and impact of each change and ensure traceability and transparency.
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
Explanation:
Smoothing is a conflict resolution technique that involves minimizing or ignoring the differences between the parties and focusing on the common interests or goals1.It is often used when the conflict is not very important or when there is a need to maintain harmony and relationships2. By using smoothing, the project manager can reduce the tension and stress caused by the disagreement and encourage the team members to cooperate and work together.Smoothing is different from compromising, which involves finding a middle ground or a trade-off that partially satisfies both parties; forcing, which involves imposing one's own solution or decision on the other party; and collaborating, which involves finding a win-win solution that fully satisfies both parties3.Reference=CompTIA Project+ PK0-005 Certification Study Guide, Chapter 10: Executing Projects Part 1, page 297;A Quick Guide to Resource Smoothing: Definition, Benefits, and Process, Conflict Resolution Techniques section;Resource Smoothing: How To Use In Project Management | Hive, Smoothing section.
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
Explanation:
The next step after defining tasks, durations, resources, and costs is to establish baselines. A baseline is an approved version of a project plan that serves as a reference point for measuring progress and performance throughout the project lifecycle. A baseline typically includes scope, schedule, cost, quality, and risk parameters. Establishing baselines involves presenting the project plan to key stakeholders and obtaining their formal agreement on the project objectives and deliverables. Baseline approval can help to establish clear expectations, avoid scope creep, and facilitate change control during project execution34
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
Explanation:
During the stabilization phase of recently deployed software, the project manager will most likely use a defect log to track and manage reported bugs. A defect log is a document that contains information about the defects or issues identified during testing or after the deployment of software. It includes the severity of the defect, the steps to reproduce the problem, and the actions taken to resolve the defect. Reference: CompTIA Project+ Study Guide Section 4.1.
The project manager will most likely use a defect log during the stabilization phase for recently deployed software to record a bug that is compromising data integrity. A defect log is a tool that tracks and documents any errors or flaws found in a software product or system during testing or operation. It usually includes information such as defect ID, description, severity, priority, status, resolution, and responsible person. A defect log can help to monitor and manage the quality of the software product or system and ensure that all defects are identified and resolved before delivery or release.
Which of the following factors would be impacted the most by requirements for a project to implement an air quality control system at a coal plant?
During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?
Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?
Explanation:
A project evaluation review is a tool that helps a project manager assess the activities performed, work effort applied, and the productivity of a project. It involves collecting and analyzing data on the project's performance, outcomes, and impacts. It also provides feedback and recommendations for improvement and learning. A project evaluation review can be done at different stages of the project life cycle, such as during or after completion. Reference = CompTIA Project+ PK0-005 Certification Study Guide, Chapter 14: Project Evaluation and Assessment; CompTIA Project+ Certification Exam Objectives, Domain 4: Project Closure, Objective 4.1: Conduct project closure activities.
A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:
* Two developers
* High uncertainty about existing systems
* Risk of frequent requirement changes
* Tight deadlines
Which of the following project methodologies would be best to use in this situation?
Explanation:
This answer is based on the best practice of choosing a project management methodology that suits the project characteristics and environment12.Scrum is an agile framework that is designed to handle complex and uncertain projects with frequent changes and tight deadlines34.Scrum involves a small, cross-functional team that works in short iterations called sprints, delivering incremental and potentially shippable products at the end of each sprint5.Scrum also allows for continuous feedback and improvement through daily stand-up meetings, sprint reviews, and retrospectives6.Scrum is suitable for this project because it can accommodate the high uncertainty, the risk of requirement changes, and the tight deadlines, while also enabling the two developers to collaborate effectively and deliver value to the customer.Reference= CompTIA Project+ Certification Study Guide7, CompTIA Project+ Certification Exam Objectives8, Project Management Methodologies Comparison (11 PM Methods)6, Project Management Methodologies: 12 Best Frameworks [2023]7, What is Scrum?5, Scrum Methodology: The Ultimate Guide6
Which of the following is the main reason for documenting artifacts?
Explanation:
Documenting artifacts is the main reason for creating and maintaining project documents that relate to the management of the project, not the project deliverables. Artifacts are used to define, support, and align the project work to the project requirements and business goals.They also serve as a source of information and evidence for future projects, audits, reviews, and lessons learned1.Documenting artifacts helps to capture the project's history, performance, outcomes, and best practices, which can be useful for organizational learning and improvement2.Reference=CompTIA Project+ PK0-005 Certification Study Guide, Chapter 14: Closing the Project, page 403;Project Artifacts and How to Use Them - Rebel's Guide to Project Management, Introduction and What are project artifacts in project management? sections;Project Management Artifacts: Definition, Types, and Phases, Introduction and What are project artifacts in project management? sections.
Before a configuration can be made to a system in development, a document containing information about how the new system will interact with other systems within the organization needs to be written. Which of the following relationships best describes this scenario?
Question