Question 221

Report Export Collapse

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

Become a Premium Member for full access
  Unlock Premium Member

Question 222

Report Export Collapse

After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

Become a Premium Member for full access
  Unlock Premium Member

Question 223

Report Export Collapse

Which of the following is the best example of a breach of physical security?

Become a Premium Member for full access
  Unlock Premium Member

Question 224

Report Export Collapse

A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

Become a Premium Member for full access
  Unlock Premium Member

Question 225

Report Export Collapse

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

Become a Premium Member for full access
  Unlock Premium Member

Question 226

Report Export Collapse

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

Become a Premium Member for full access
  Unlock Premium Member

Question 227

Report Export Collapse

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the following has the project manager identified?

Become a Premium Member for full access
  Unlock Premium Member

Question 228

Report Export Collapse

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Become a Premium Member for full access
  Unlock Premium Member

Question 229

Report Export Collapse

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

Become a Premium Member for full access
  Unlock Premium Member

Question 230

Report Export Collapse

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

Become a Premium Member for full access
  Unlock Premium Member
Total 299 questions