Question 81

Report Export Collapse

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

Smoke testing
Smoke testing
Regression testing
Regression testing
Unit testing
Unit testing
User acceptance testing
User acceptance testing
Suggested answer: B
Explanation:

Regression testing is a type of testing that is done on an existing system to ensure that the previous functionality still works after a change has been made. Regression testing is a process of retesting or verifying that a software system or application still performs as expected after it has been modified or updated with new features, bug fixes, patches, etc. Regression testing can help to detect any errors or defects that may have been introduced by the change and ensure that no functionality has been broken or degraded.


asked 02/10/2024
Piotr Jakubowski
44 questions

Question 82

Report Export Collapse

To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?

Process moving
Process moving
Brainstorming
Brainstorming
Interview
Interview
Focus group
Focus group
Suggested answer: D
Explanation:

A focus group is a technique that involves bringing together a group of stakeholders and facilitating a discussion to elicit their opinions, needs, and expectations about the project. This technique can help to gather requirements from stakeholders in an interactive and collaborative way1, p. 67

asked 02/10/2024
Emmanuel ogoro
38 questions

Question 83

Report Export Collapse

Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?

Telephone
Telephone
Videoconference
Videoconference
Face-to-face
Face-to-face
Email
Email
Suggested answer: D
Explanation:

Email is a communication tool that allows the project manager to send information to one or more recipients without requiring immediate feedback or confirmation of receipt. Email can be used to broadcast information that is not urgent or critical, such as status updates, meeting minutes, or general announcements1, p. 75

asked 02/10/2024
Jason Coleman
45 questions

Question 84

Report Export Collapse

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

Escalate directly to the project sponsor
Escalate directly to the project sponsor
Push the kickoff meeting out by one week
Push the kickoff meeting out by one week
Proceed with the kickoff as planned
Proceed with the kickoff as planned
Identity replacements for project stakeholders
Identity replacements for project stakeholders
Suggested answer: A
Explanation:

The project sponsor is the person who provides the authority, funding, and support for the project.

The project sponsor can also help to influence and engage the key stakeholders who are essential for the success of the project. If several stakeholders have declined the invitation for the kickoff meeting,

which is an important event to establish the vision, scope, and expectations of the project, the project manager should escalate this issue to the project sponsor and seek their assistance to ensure the participation of the stakeholders1, p. 47

asked 02/10/2024
Jaroslaw Walaszek
49 questions

Question 85

Report Export Collapse

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

Project status report
Project status report
Requirements Traceability Matrix
Requirements Traceability Matrix
Detect log
Detect log
Signed project charter
Signed project charter
Work breakdown structure
Work breakdown structure
Suggested answer: A
asked 02/10/2024
Clive Roberts
50 questions

Question 86

Report Export Collapse

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

Data management
Data management
Issue management
Issue management
Work breakdown structure
Work breakdown structure
Document management
Document management
Communication management
Communication management
Risk management
Risk management
Suggested answer: A, D
Explanation:

A strategy to store records must include data management and document management as two essential elements. Data management is the process of ensuring that the data collected, stored, and used by the project is accurate, complete, consistent, secure, and accessible. Data management helps to maintain the quality and integrity of the project data and supports the analysis and reporting of the project outcomes1, p. 4

Document management is the process of creating, organizing, storing, retrieving, and disposing of project documents in a systematic and controlled way. Document management helps to ensure that the project documents are available, reliable, usable, and authentic throughout the project life cycle and beyond. Document management also helps to comply with the legal, regulatory, and organizational requirements for records retention and disposition2, p. 3

asked 02/10/2024
justen layne
44 questions

Question 87

Report Export Collapse

When introducing a new information asset, what is the MOST important responsibility of the asset owner?

Information disposal
Information disposal
Information classification
Information classification
Information access administration
Information access administration
Information backup
Information backup
Suggested answer: B
Explanation:

The most important responsibility of an asset owner when introducing a new information asset is information classification. This process involves determining the level of sensitivity and the appropriate handling of the asset. Classification helps in applying the right security controls and access permissions, ensuring that the asset is protected according to its value and sensitivity.

Reference= CompTIA Project+ Certification Study Guide (PK0-005)

asked 02/10/2024
Dylan Ogle
54 questions

Question 88

Report Export Collapse

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Compromising
Compromising
Forcing
Forcing
Smoothing
Smoothing
Collaborating
Collaborating
Suggested answer: C
Explanation:

Smoothing is a conflict resolution technique that involves minimizing or ignoring the differences between the parties and focusing on the common interests or goals1.It is often used when the conflict is not very important or when there is a need to maintain harmony and relationships2. By using smoothing, the project manager can reduce the tension and stress caused by the disagreement and encourage the team members to cooperate and work together.Smoothing is different from compromising, which involves finding a middle ground or a trade-off that partially satisfies both parties; forcing, which involves imposing one's own solution or decision on the other party; and collaborating, which involves finding a win-win solution that fully satisfies both parties3.Reference=CompTIA Project+ PK0-005 Certification Study Guide, Chapter 10: Executing Projects Part 1, page 297;A Quick Guide to Resource Smoothing: Definition, Benefits, and Process, Conflict Resolution Techniques section;Resource Smoothing: How To Use In Project Management | Hive, Smoothing section.

asked 02/10/2024
Sasa Korlat
37 questions

Question 89

Report Export Collapse

A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?

Milestone
Milestone
Gantt
Gantt
Burndown
Burndown
PERT
PERT
Suggested answer: A
Explanation:

A milestone chart is the best chart to use to show major accomplishments for key events, because it displays the important deliverables or outcomes of a project along a timeline12.A milestone chart can provide a high-level overview of the project progress and achievements, without showing the details of each task or activity34.A milestone chart can also help communicate the project status and expectations to the stakeholders, and identify any potential risks or delays that may affect the project completion56.Reference= CompTIA Project+ Certification Study Guide7, CompTIA Project+ Certification Exam Objectives8, What is a Milestone Chart?1, How to Create a Milestone Chart in Excel in 3 Steps2, Milestone Chart: The Easiest Way to Track Project Milestones3, How to Use Milestones in Project Management4

asked 02/10/2024
Jason Coleman
45 questions

Question 90

Report Export Collapse

Which of the following statements best describes a content management system?

A system to manage electronic signatures and document workflow
A system to manage electronic signatures and document workflow
A system to manage database integration and provide messaging services
A system to manage database integration and provide messaging services
A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish
A system to manage shared data on the web, allowing multiple contributors to create, edit, and publish
A system to manage documents archival, such as emails, spreadsheets, and support tickets
A system to manage documents archival, such as emails, spreadsheets, and support tickets
Suggested answer: C
Explanation:

A content management system (CMS) is a software application that allows users to create, manage, and deliver content via digital channels, such as websites, blogs, or social media12.A CMS enables multiple contributors to access, edit, and publish content without requiring technical knowledge or coding skills34.A CMS also provides features such as templates, workflows, media libraries, and analytics to help users design, organize, and optimize their content56.Reference= CompTIA Project+ Certification Study Guide7, CompTIA Project+ Certification Exam Objectives8, What Is a Content Management System (CMS)?1, What is a Content Management System (CMS) | Oracle2, What is a Content Management System (CMS)?| Adobe Basics3, What is a CMS?4, What is a Content Management System?5, Content Management System (CMS) - Definition from Techopedia6

asked 02/10/2024
Daniel Bucknor-Ankrah
44 questions
Total 299 questions
Go to page: of 30
Search

Related questions