ExamGecko
Home / CompTIA / PK0-005 / List of questions
Ask Question

CompTIA PK0-005 Practice Test - Questions Answers, Page 2

Add to Whishlist

List of questions

Question 11

Report Export Collapse

By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

Allocate resources.
Allocate resources.
Determine the project budget
Determine the project budget
Develop a communication plan.
Develop a communication plan.
Establish baselines.
Establish baselines.
Suggested answer: D
Explanation:

The next step after defining tasks, durations, resources, and costs is to establish baselines. A baseline is an approved version of a project plan that serves as a reference point for measuring progress and performance throughout the project lifecycle. A baseline typically includes scope, schedule, cost, quality, and risk parameters. Establishing baselines involves presenting the project plan to key stakeholders and obtaining their formal agreement on the project objectives and deliverables. Baseline approval can help to establish clear expectations, avoid scope creep, and facilitate change control during project execution34

asked 02/10/2024
Miguel Monteiro
43 questions

Question 12

Report Export Collapse

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

RFI
RFI
RACI
RACI
WBS
WBS
SOW
SOW
Suggested answer: B
Explanation:

The RACI (Responsible, Accountable, Consulted, Informed) matrix is used to document which resources are responsible for which tasks. The RACI matrix is a tool that helps to clarify roles and responsibilities on a project. It assigns a level of responsibility to each resource involved in the project. Reference: CompTIA Project+ Study Guide Section 3.4.

The project manager should use a RACI matrix to document which resources are responsible for which tasks. A RACI matrix is a type of responsibility assignment matrix (RAM) that plots the roles and responsibilities of resources on a project team. RACI stands for Responsible, Accountable,

Consulted, and Informed. A RACI matrix can help to clarify who does what on a project, avoid confusion and duplication of work, and improve communication and collaboration among team members.

asked 02/10/2024
Ayyaz Rehan Ikram
32 questions

Question 13

Report Export Collapse

During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

SLA
SLA
TOR
TOR
SOW
SOW
NDA
NDA
Suggested answer: C
Explanation:

In order to find the client billing rate for a particular engineer, the project manager would need to refer to the SOW (Statement of Work). The SOW is a document that outlines the work to be performed, the timeframe for completion, and the cost of the project. It also includes information about the resources involved in the project and their billing rates. Reference: CompTIA Project+

Study Guide Section 2.2.

The project manager would need a statement of work (SOW) to find information about the client billing rate for a particular engineer. A SOW is a document that defines the scope of work for a project or contract. It usually includes information such as deliverables, milestones, timeline, costs, payment terms, quality standards, and acceptance criteria. A SOW can help to specify what services or products will be provided by whom, when, where, how, and for how much.

asked 02/10/2024
Kurt Van Rymenant
52 questions

Question 14

Report Export Collapse

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

Approving the change request
Approving the change request
Developing a rollback plan
Developing a rollback plan
Gathering necessary resources
Gathering necessary resources
Defining requirements
Defining requirements
Suggested answer: B
Explanation:

When implementing an IT infrastructure change that takes risks into consideration, the project manager should develop a rollback plan. A rollback plan is a contingency plan that outlines the steps that need to be taken in case the change does not work as expected. It includes a plan to roll back the changes and restore the system to its previous state. Reference: CompTIA Project+ Study Guide

Section 3.3.

The project manager should develop a rollback plan when implementing an IT infrastructure change that takes risks into consideration. A rollback plan is a contingency plan that describes how to revert back to the previous state of the system in case of a failure or disruption during the change implementation. A rollback plan can help to minimize the impact of the change on the system performance and availability and ensure business continuity and data integrity.

asked 02/10/2024
Mohamed Iftiquar Aslam Hameed
42 questions

Question 15

Report Export Collapse

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

Issue log
Issue log
Defect log
Defect log
Change log
Change log
Task board
Task board
Suggested answer: B
Explanation:

During the stabilization phase of recently deployed software, the project manager will most likely use a defect log to track and manage reported bugs. A defect log is a document that contains information about the defects or issues identified during testing or after the deployment of software. It includes the severity of the defect, the steps to reproduce the problem, and the actions taken to resolve the defect. Reference: CompTIA Project+ Study Guide Section 4.1.

The project manager will most likely use a defect log during the stabilization phase for recently deployed software to record a bug that is compromising data integrity. A defect log is a tool that tracks and documents any errors or flaws found in a software product or system during testing or operation. It usually includes information such as defect ID, description, severity, priority, status, resolution, and responsible person. A defect log can help to monitor and manage the quality of the software product or system and ensure that all defects are identified and resolved before delivery or release.

asked 02/10/2024
fadi kako
50 questions

Question 16

Report Export Collapse

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

ESG
ESG
PHI
PHI
Pll
Pll
ROI
ROI
Suggested answer: A
Explanation:

The project manager should have considered environmental, social, and governance (ESG) factors during initial planning to prevent the situation of receiving a penalty for disposing of some computers improperly. ESG factors are criteria that measure the sustainability and ethical impact of an organization's activities. They include aspects such as environmental protection, social responsibility, human rights, diversity, and corporate governance. Considering ESG factors can help to reduce risks, improve reputation, and enhance performance of an organization12

asked 02/10/2024
megat ilham
40 questions

Question 17

Report Export Collapse

A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

Multiauthoring software
Multiauthoring software
Word processor
Word processor
Real-time polling
Real-time polling
Conferencing platforms
Conferencing platforms
Suggested answer: A
Explanation:

The project manager is using multiauthoring software to maintain the version control for the documentation of requirements. Multiauthoring software is a type of software that allows multiple users to create, edit, and collaborate on documents simultaneously. It also provides features such as tracking changes, commenting, reviewing, and merging versions. Multiauthoring software can help to improve the quality, accuracy, and consistency of documents and facilitate communication and feedback among stakeholders. Examples of multiauthoring software include Google Docs, Microsoft

Word Online, and Confluence34

asked 02/10/2024
Shady Mohamed Ibrahim
36 questions

Question 18

Report Export Collapse

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

External
External
Internal
Internal
Mandatory
Mandatory
Discretionary
Discretionary
Suggested answer: C
Explanation:

The dependency between software installation and desktop installation is a mandatory dependency.

A mandatory dependency is a type of dependency that is inherent in the nature or logic of the work and cannot be avoided or changed. It is also known as a hard dependency or a hard logic dependency. A mandatory dependency means that one task must be completed before another task can start or finish. For example, software installation can only start after desktop installation is finished5

The dependency between desktop installation and software installation represents a mandatory dependency. A mandatory dependency is a type of task dependency that is inherent in the nature of the work being performed. In this case, software installation cannot begin until desktops are installed and powered on, and therefore, the dependency is mandatory. Reference: CompTIA Project+ Study

Guide, Chapter 3: Project Integration Management, Objective 3.1: Identify the project management processes and the interactions between them.

asked 02/10/2024
Tamilselvi R
41 questions

Question 19

Report Export Collapse

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

Issue log
Issue log
Gantt chart
Gantt chart
Milestone chart
Milestone chart
Change control log
Change control log
Suggested answer: D
Explanation:

The project manager should use a change control log to document the effects of the hurricane delay on the project. A change control log is a tool that records and tracks any changes that occur during the project lifecycle. It usually includes information such as change ID, description, impact, status, approval, and resolution. A change control log can help to monitor and manage the changes that affect the project scope, schedule, cost, quality, or resources and ensure that they are aligned with the project objectives and stakeholder expectations.

asked 02/10/2024
matias alvarez
35 questions

Question 20

Report Export Collapse

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Project change management plan
Project change management plan
Project management plan
Project management plan
Project transition plan
Project transition plan
Project communication plan
Project communication plan
Suggested answer: B
Explanation:

The project manager should use the project management plan to document the input from the stakeholders on the minimum viable product that would be acceptable for the project. The project management plan is a document that describes how the project will be executed, monitored, controlled, and closed. It usually includes information such as scope statement, work breakdown structure (WBS), schedule baseline, cost baseline, quality plan, risk plan, communication plan, stakeholder plan, and change management plan. The project management plan can help to define and communicate the project requirements, deliverables, assumptions, constraints, and expectations to all stakeholders involved in the project.

The project management plan would be used to document the input obtained from stakeholders during the meeting to review the requirements and agree on the minimum viable product. The project management plan is a comprehensive document that outlines the approach, scope, schedule, budget, quality, resources, and communication for a project. The document is updated throughout the project lifecycle and serves as a guide for project execution, monitoring, and control. Reference:

CompTIA Project+ Study Guide, Chapter 3: Project Integration Management, Objective 3.3: Identify the components of the project management plan.

asked 02/10/2024
Victor vila
44 questions
Total 299 questions
Go to page: of 30
Search

Related questions