CompTIA PK0-005 Practice Test - Questions Answers, Page 10

List of questions
Question 91

Which of the following pieces of data are examples of Pll?
Question 92

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?
Question 93

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?
Question 94

Which of the following is the main reason for documenting artifacts?
Question 95

A project manager has decided to wait until all requirements are developed to initiate testing. Which of the following relationship dependencies is the project manager using?
Question 96

As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).
Question 97

Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).
Question 98

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?
Question 99

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?
Question 100

Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?
Question