ExamGecko
Home / CompTIA / PK0-005 / List of questions
Ask Question

CompTIA PK0-005 Practice Test - Questions Answers, Page 8

Add to Whishlist

List of questions

Question 71

Report Export Collapse

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

Kanban board
Kanban board
Pareto chart
Pareto chart
Ishikawa diagram
Ishikawa diagram
Decision tree
Decision tree
Suggested answer: C
Explanation:

An Ishikawa diagram is a tool that the project team should use to find the cause of the defects associated with project deliverables. An Ishikawa diagram, also known as a fishbone diagram or a cause-and-effect diagram, is a graphical tool that shows the possible causes of a problem or effect using a fishbone-like structure. An Ishikawa diagram can help to identify and analyze the root causes of defects or issues and find solutions to prevent or eliminate them.

asked 02/10/2024
Amin Dashti
55 questions

Question 72

Report Export Collapse

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

Dashboard
Dashboard
Gantt chart
Gantt chart
Work breakdown structure
Work breakdown structure
Requirements Traceability Matrix
Requirements Traceability Matrix
Suggested answer: A
Explanation:

A dashboard is a tool that the project manager will most likely use to update the project sponsor and senior stakeholders about the progress of a project. A dashboard is a graphical tool that displays key performance indicators (KPIs), metrics, and data related to a project using charts, graphs, tables, or other visual elements. A dashboard can help to provide a quick and easy overview of the project status and performance and highlight any issues or risks that need attention.

asked 02/10/2024
Dave Breath
56 questions

Question 73

Report Export Collapse

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

Critical paths
Critical paths
Resources
Resources
Milestones
Milestones
Work breakdown structures
Work breakdown structures
Suggested answer: C
Explanation:

Milestones are activities with zero duration that are added to a project schedule by a project manager. Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task. Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.

asked 02/10/2024
Tyler Evans
42 questions

Question 74

Report Export Collapse

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Become a Premium Member for full access
  Unlock Premium Member

Question 75

Report Export Collapse

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

Become a Premium Member for full access
  Unlock Premium Member

Question 76

Report Export Collapse

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Become a Premium Member for full access
  Unlock Premium Member

Question 77

Report Export Collapse

A PM learns about some communication issues with different stakeholders and team members.

Which of the following should the PM do NEXT?

Become a Premium Member for full access
  Unlock Premium Member

Question 78

Report Export Collapse

An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

Become a Premium Member for full access
  Unlock Premium Member

Question 79

Report Export Collapse

An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?

Become a Premium Member for full access
  Unlock Premium Member

Question 80

Report Export Collapse

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

Become a Premium Member for full access
  Unlock Premium Member
Total 372 questions
Go to page: of 38
Search

Related questions