A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

A.
Creation of a social news forum
A.
Creation of a social news forum
Answers
B.
Management directives to use the new system
B.
Management directives to use the new system
Answers
C.
New user kickoff meeting
C.
New user kickoff meeting
Answers
D.
Monthly feedback and training sessions
D.
Monthly feedback and training sessions
Answers
Suggested answer: D

Explanation:

Monthly feedback and training sessions are the best approach to ensure that the deliverables of a critical business initiative are increasingly adopted and leveraged by the organization over time.

Feedback and training sessions are communication and learning activities that provide information and guidance on how to use and benefit from the new processes and technology introduced by the initiative. Feedback and training sessions can help to increase awareness, understanding, acceptance, and adoption of the deliverables among the organization's employees and stakeholders.

They can also help to identify and address any issues or challenges that may arise during the implementation and transition phases.

A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis:

Based on the chart, which of the following is the current status of the project?

A.
Behind schedule and over budget
A.
Behind schedule and over budget
Answers
B.
Behind schedule and under budget
B.
Behind schedule and under budget
Answers
C.
Ahead of schedule and over budget
C.
Ahead of schedule and over budget
Answers
D.
Ahead of schedule and under budget
D.
Ahead of schedule and under budget
Answers
Suggested answer: A

Explanation:

The project manager can use the burn up chart to analyze the current status of the project based on its scope (value delivered), budget (cost), and schedule (time). A burn up chart is a graphical tool that shows how much work has been completed (burned up) versus how much work remains (scope) over time. It also shows how much budget has been spent (burned up) versus how much budget remains (budget) over time. A burn up chart can help to monitor and control the project progress and performance and identify any variances or deviations from the plan. The chart given shows that both scope and budget lines are above their respective target lines at any given time point. This means that less work has been completed than planned (scope variance) and more money has been spent than planned (budget variance) at any given time point. Therefore, the project is behind schedule and over budget.

Which of the following criteria would favor using the agile methodology to manage an upcoming project?

A.
Strong projectized organization
A.
Strong projectized organization
Answers
B.
Medium risk
B.
Medium risk
Answers
C.
Lack of resources
C.
Lack of resources
Answers
D.
Multiple undefined tasks
D.
Multiple undefined tasks
Answers
Suggested answer: D

Explanation:

Multiple undefined tasks would favor using the agile methodology to manage an upcoming project. Agile methodology is a project management framework that breaks projects down into several dynamic phases, commonly known as sprints. Agile methodology is an iterative and adaptive approach that allows teams to respond to changing requirements and customer feedback quickly and effectively. Agile methodology is suitable for projects that have multiple undefined tasks, as it enables teams to prioritize and deliver the most valuable features first, and refine and improve them over time based on user input and testing12

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?

A.
RFP
A.
RFP
Answers
B.
WBS
B.
WBS
Answers
C.
SLA
C.
SLA
Answers
D.
SOW
D.
SOW
Answers
Suggested answer: D

Explanation:

The client provided a statement of work (SOW) to the project manager and suggested that the project manager and team just need to execute the plan. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly timeconsuming project was executed previously in the organization. Which of the following actions should the PM take?

A.
Perform a root cause analysis.
A.
Perform a root cause analysis.
Answers
B.
Organize a stakeholder meeting
B.
Organize a stakeholder meeting
Answers
C.
Escalate the issue to the CCB
C.
Escalate the issue to the CCB
Answers
D.
Contact the PMO for assistance.
D.
Contact the PMO for assistance.
Answers
Suggested answer: D

Explanation:

The project manager should contact the project management office (PMO) for assistance after learning that a similarly time-consuming project was executed previously in the organization. A PMO is a department or group within an organization that provides centralized guidance, governance, standards, best practices, resources, and oversight for project management activities. A PMO can help the project manager by providing access to historical data, lessons learned, templates, tools, methodologies, and expertise from previous projects that can be useful for planning and executing the current project.

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

A.
A project manager assigned the wrong resources.
A.
A project manager assigned the wrong resources.
Answers
B.
A project manager did not release the resources
B.
A project manager did not release the resources
Answers
C.
A project manager did not remove the system access.
C.
A project manager did not remove the system access.
Answers
D.
A project manager did not provide the project sign-off.
D.
A project manager did not provide the project sign-off.
Answers
Suggested answer: B

Explanation:

A project manager did not release the resources. A project manager not releasing the resources could most likely be the cause of this issue where several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Releasing resources is a process of freeing up or reallocating any human or material resources that were used for a project after its completion or closure. Releasing resources can help to update the resource availability and utilization records and avoid any conflicts or errors in resource allocation or reporting.

Which of the following requires the MOST availability from the business team?

A.
SDLC
A.
SDLC
Answers
B.
Scrum
B.
Scrum
Answers
C.
PRINCE2
C.
PRINCE2
Answers
D.
Waterfall
D.
Waterfall
Answers
Suggested answer: B

Explanation:

Scrum requires the most availability from the business team among the given options. Scrum is a popular agile framework that organizes work into short iterations called sprints, usually lasting one to four weeks. Scrum emphasizes collaboration between teams, customers, and stakeholders and encourages open communication and transparency throughout the project lifecycle. Scrum requires frequent involvement and feedback from the business team through activities such as product backlog refinement, sprint planning, sprint review, sprint retrospective, and daily scrum meetings.

Which of the following software programs would be BEST to use lo store information related to business transactions?

A.
Record management system
A.
Record management system
Answers
B.
Customer relationship management
B.
Customer relationship management
Answers
C.
Enterprise resource planning
C.
Enterprise resource planning
Answers
D.
Content management system
D.
Content management system
Answers
Suggested answer: B

Explanation:

Customer relationship management (CRM) software would be the best to use to store information related to business transactions. CRM software is a type of software that helps businesses manage their interactions and relationships with current and potential customers. CRM software can store and organize information such as customer contact details, purchase history, preferences, feedback, complaints, etc. CRM software can help businesses improve customer service, satisfaction, loyalty, retention, and revenue1

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

A.
Work with the project scheduler to update the project timeline.
A.
Work with the project scheduler to update the project timeline.
Answers
B.
Communicate to the stakeholders about the updated timeline.
B.
Communicate to the stakeholders about the updated timeline.
Answers
C.
Ask the development team to fast-track upcoming activities.
C.
Ask the development team to fast-track upcoming activities.
Answers
D.
Add two resources so the critical activities will finish on time.
D.
Add two resources so the critical activities will finish on time.
Answers
Suggested answer: A

Explanation:

Work with the project scheduler to update the project timeline. The project manager should work with the project scheduler to update the project timeline after finding an unforeseen dependency on one of the critical project activities that will most likely cause a delay. The project scheduler is a person or a tool that helps plan, schedule, monitor, and control the project activities and resources.

The project scheduler can help the project manager to assess the impact of the dependency on the project schedule and identify any possible ways to mitigate or resolve it. The project scheduler can also help to update the project timeline with the revised dates and durations of the project activities and communicate them to the relevant stakeholders.

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

A.
Memorandum of understanding
A.
Memorandum of understanding
Answers
B.
Request for information
B.
Request for information
Answers
C.
Statement of work
C.
Statement of work
Answers
D.
Non-disclosure agreement
D.
Non-disclosure agreement
Answers
Suggested answer: B

Explanation:

The statement of work (SOW) would be the next document that a project manager should update once the need to procure goods and/or services is identified. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.