ExamGecko
Home / CompTIA / PK0-005 / List of questions
Ask Question

CompTIA PK0-005 Practice Test - Questions Answers, Page 4

Add to Whishlist

List of questions

Question 31

Report Export Collapse

A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

Collate the lessons learned.
Collate the lessons learned.
Perform a gap analysis.
Perform a gap analysis.
Review existing artifacts.
Review existing artifacts.
Conduct a retrospective.
Conduct a retrospective.
Suggested answer: C
Explanation:

The project manager should review existing artifacts to get an understanding of the purpose of the project. Existing artifacts are documents or records that provide information about the project background, context, scope, objectives, requirements, stakeholders, and deliverables. They may include documents such as project proposal, project charter, business case, feasibility study, statement of work (SOW), or contract. Reviewing existing artifacts can help to clarify the project vision and expectations and provide a basis for planning and executing the project.

asked 02/10/2024
marco giovinazzo
33 questions

Question 32

Report Export Collapse

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?

Social engineering
Social engineering
Phishing
Phishing
Spoofing
Spoofing
Hacking
Hacking
Suggested answer: B
Explanation:

Phishing is a scenario where someone claiming to be from a legitimate organization sends an email or other message to a target person asking for sensitive information or access to a system or account. Phishing is a type of cyberattack that aims to trick the target into revealing personal or financial data or installing malware on their device. Phishing can compromise the security and privacy of the target and expose them to identity theft, fraud, or other malicious activities.

asked 02/10/2024
Olanrewaju Abolanle
36 questions

Question 33

Report Export Collapse

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

Responsibility assignment matrix
Responsibility assignment matrix
Acceptable communication channels
Acceptable communication channels
Risk registry
Risk registry
Staff directory
Staff directory
Suggested answer: B
Explanation:

The project manager should have prepared acceptable communication channels to avoid the situation of a stakeholder not replying to emails due to intermittent Internet service. Acceptable communication channels are methods or modes of communication that are agreed upon by all parties involved in a project. They may include aspects such as email, phone call, text message, video conference, instant message, or face-to-face meeting. Acceptable communication channels can help to ensure that messages are delivered and received effectively and efficiently and that communication preferences and limitations are respected.

asked 02/10/2024
Francisco Sanchez Valdes
44 questions

Question 34

Report Export Collapse

A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.

CompTIA PK0-005 image Question 34 96924 10022024175307000000

Which of the following is the current status of the process?

Based on the rule of seven, the process is under control
Based on the rule of seven, the process is under control
The amount of data is insufficient to determine if quality is low.
The amount of data is insufficient to determine if quality is low.
The process is out of control and should be revised.
The process is out of control and should be revised.
The goal should be adjusted since most of the data points are close to the lower limit.
The goal should be adjusted since most of the data points are close to the lower limit.
Suggested answer: C
Explanation:

The process is out of control and should be revised. The project manager can use the rule of seven to determine the status of the process based on the control chart. The rule of seven states that if seven or more consecutive measurements fall on one side of the mean that there's an assignable cause that needs investigation. In this case, the last seven data points are all below the mean, which indicates that the process is out of control and in need of adjustment12

asked 02/10/2024
Vishal Vitthal Pawar
47 questions

Question 35

Report Export Collapse

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

Continuous integration
Continuous integration
Rollback plan
Rollback plan
Customer notification
Customer notification
Automated testing
Automated testing
Suggested answer: C
Explanation:

Customer notification should be added to the issue log after receiving an escalation from an executive about the extension of the downtime after the scheduled window. Customer notification is a communication activity that informs the customers about any issues or changes that may affect their satisfaction or expectations. Customer notification can help to maintain trust, transparency, and goodwill with the customers and prevent any negative impacts on their business operations or experience.

asked 02/10/2024
Rick James
47 questions

Question 36

Report Export Collapse

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

Communicate with the affected stakeholders.
Communicate with the affected stakeholders.
Initiate a formal change request to modify the cost
Initiate a formal change request to modify the cost
Adjust the scope to stay within the cost.
Adjust the scope to stay within the cost.
Set a new cost using a lightweight estimation method.
Set a new cost using a lightweight estimation method.
Suggested answer: A
Explanation:

The project manager should communicate with the affected stakeholders first after realizing that the sign-off for the project scope baseline is delayed due to multiple changes and that the budget for this project is restricted by the project sponsor. The affected stakeholders are those who have an interest or influence on the project and may be impacted by any changes or delays. Communicating with them can help to explain the situation, assess the impact, seek feedback, and manage expectations.

asked 02/10/2024
Barbara Bailey
44 questions

Question 37

Report Export Collapse

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

Document the request in the change control log.
Document the request in the change control log.
Communicate the change deployment.
Communicate the change deployment.
Conduct an impact assessment.
Conduct an impact assessment.
Implement the change.
Implement the change.
Suggested answer: B
Explanation:

The project manager should communicate the change deployment next after updating the project plan with the newest project end date as a result of an approved change. Communicating the change deployment involves informing all relevant parties about when and how the change will be implemented and what are the expected outcomes and benefits. Communicating the change deployment can help to ensure alignment, readiness, and support for the change and avoid any confusion or resistance.

asked 02/10/2024
Jag Patel
37 questions

Question 38

Report Export Collapse

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

CompTIA PK0-005 image Question 38 96928 10022024175307000000

B)

CompTIA PK0-005 image Question 38 96928 10022024175307000000

C)

CompTIA PK0-005 image Question 38 96928 10022024175307000000

D)

CompTIA PK0-005 image Question 38 96928 10022024175307000000

Option A
Option A
Option B
Option B
Option C
Option C
Option D
Option D
Suggested answer: C
Explanation:

Option C shows a graph that most likely represents the observed relationship in this scenario. The graph shows a learning curve, which is a graphical representation of the relationship between a learner's performance on a task and the number of attempts or time required to complete the task.

The learning curve theory proposes that a learner's efficiency in a task improves over time the more the learner performs the task. In this case, the IT intern was able to complete more set-ups in less time as they gained more experience and proficiency over the two-week rotation12

asked 02/10/2024
Shirish Astagikar
47 questions

Question 39

Report Export Collapse

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

Exploit the risk.
Exploit the risk.
Accept the risk.
Accept the risk.
Avoid the risk.
Avoid the risk.
Transfer the risk.
Transfer the risk.
Suggested answer: A
Explanation:

The project manager should exploit the risk after an opportunity emerged in the middle of a project life cycle. Exploit is a risk response strategy that aims to increase the probability and/or impact of a positive risk or opportunity. Exploit can involve actions such as allocating more resources, changing the scope or schedule, or adding more features or benefits to the project deliverables. Exploit can help to ensure that the opportunity is realized and that the project gains more value or advantage from it3

asked 02/10/2024
Dirk Lamberts
49 questions

Question 40

Report Export Collapse

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

Data warehouse
Data warehouse
SQL database
SQL database
Multitier architecture
Multitier architecture
Content management system
Content management system
Suggested answer: C
Explanation:

Multitier architecture is a type of software architecture that is suitable to support enterprise-level client-server solutions. Multitier architecture divides an application into logical layers or tiers that are distributed among different servers or machines. Each tier performs a specific function or role and communicates with other tiers through well-defined interfaces. Multitier architecture can provide benefits such as scalability, performance, security, maintainability, and reusability for complex and large-scale applications.

asked 02/10/2024
Adrian Petrisoaia
44 questions
Total 299 questions
Go to page: of 30
Search

Related questions