Question 41

Report Export Collapse

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

Review the detailed plan.
Review the detailed plan.
Develop a preliminary scope.
Develop a preliminary scope.
Develop a transition plan.
Develop a transition plan.
Develop a project management plan.
Develop a project management plan.
Review the resource pool.
Review the resource pool.
Review the project objectives.
Review the project objectives.
Suggested answer: E, F
Explanation:

Review the resource pool and review the project objectives are activities that the project manager should undertake after accepting a new project. Reviewing the resource pool involves identifying and evaluating the availability, skills, and competencies of the human and material resources that are needed for the project. Reviewing the project objectives involves understanding and clarifying the expected outcomes and benefits of the project and how they align with the organizational strategy and stakeholder expectations. These activities can help to plan and execute the project effectively and efficiently.

asked 02/10/2024
Soumia Djenan
33 questions

Question 42

Report Export Collapse

A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select

TWO).

Company vision
Company vision
Global environment
Global environment
Brand value
Brand value
Mission statement
Mission statement
Portfolio budget
Portfolio budget
Local legislation
Local legislation
Suggested answer: A, D
Explanation:

Company vision and mission statement should be considered in the evaluation of the project portfolio based on the company's strategic plan. Company vision is a statement that describes the long-term aspirations and desired future state of the organization. Company mission statement is a statement that defines the core purpose and values of the organization and how it serves its customers and stakeholders. These statements provide direction and guidance for the strategic planning and decision making of the organization. They also help to align the project portfolio with the organizational goals and objectives and ensure that the projects and programs in the portfolio deliver value and benefits to the organization12

asked 02/10/2024
leconte maxime
41 questions

Question 43

Report Export Collapse

Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?

Gantt chart
Gantt chart
Maintenance window schedule
Maintenance window schedule
Functional requirements
Functional requirements
Test results
Test results
Suggested answer: A
Explanation:

The project manager should consult a Gantt chart after the sponsor states that the project is taking too long to complete. A Gantt chart is a graphical tool that shows the schedule of a project, including the start and end dates, durations, dependencies, milestones, and progress of each task or activity. A

Gantt chart can help to monitor and control the project timeline and identify any delays, variances, or issues that may affect the project completion.

asked 02/10/2024
Sergio Pena Ochoa
44 questions

Question 44

Report Export Collapse

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

Decision board
Decision board
Whiteboard
Whiteboard
Task board
Task board
Dashboard
Dashboard
Suggested answer: C
Explanation:

A task board is a visual tool that displays team progress for stand-up meetings. A task board usually consists of columns that represent different stages or statuses of tasks, such as to do, in progress, done, or blocked. Each task is represented by a card or sticky note that can be moved across the columns as the task progresses. A task board can help to facilitate communication, collaboration, and transparency among team members and stakeholders. It can also help to track and manage work flow, prioritize tasks, identify bottlenecks, and resolve issues3

asked 02/10/2024
doaa elshazly
52 questions

Question 45

Report Export Collapse

A project manager is assigned to a multinational project with team members from different continents. Which of the following is the MOST important aspect for the project manager to consider?

Resource allocation
Resource allocation
Communication security
Communication security
Technological factors
Technological factors
Cultural differences
Cultural differences
Suggested answer: D
Explanation:

Cultural differences are the most important aspect for the project manager to consider when assigned to a multinational project with team members from different continents. Cultural differences refer to the variations in beliefs, values, norms, behaviors, customs, and communication styles among people from different countries or regions. Cultural differences can affect how team members interact, communicate, collaborate, negotiate, make decisions, solve problems, manage conflicts, and perform tasks. The project manager should be aware of and respect the cultural differences among team members and foster a positive and inclusive team culture that leverages diversity and promotes trust and cooperation.

asked 02/10/2024
Hemanth Gangabattula
40 questions

Question 46

Report Export Collapse

During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:

CompTIA PK0-005 image Question 46 96936 10022024175307000000

Which of the following was the initial cause of the issue?

Inadequate memory
Inadequate memory
Incorrect configuration
Incorrect configuration
Lack of infrastructure
Lack of infrastructure
Inadequate instructions
Inadequate instructions
Suggested answer: B
Explanation:

. Incorrect configuration was the initial cause of the issue that caused the unexpected crash of the website that the team was developing. The diagram given is an example of a fishbone diagram or a cause-and-effect diagram that shows the possible causes of a problem or effect. The diagram has four main categories: people, process, technology, and environment. Each category has subcategories that list specific factors that may contribute to the problem or effect. The diagram shows that incorrect configuration under technology was marked as an initial cause of website crash.

asked 02/10/2024
AHMED MAHMOUD NASR Hassan
38 questions

Question 47

Report Export Collapse

Which of the following describes three-tier architecture?

Conceptual, design, and implementation stages
Conceptual, design, and implementation stages
Presentation, application, and data processing
Presentation, application, and data processing
Network, software, and security
Network, software, and security
Development, testing, and production environment
Development, testing, and production environment
Suggested answer: B
Explanation:

Presentation, application, and data processing. Presentation, application, and data processing are the three logical and physical computing tiers that make up a three-tier architecture. A three-tier architecture is a type of software architecture that separates an application into three layers or tiers that run on different servers or machines. Each tier performs a specific function or role and communicates with other tiers through well-defined interfaces. The presentation tier is the user interface and communication layer of the application, where the end user interacts with the application. The application tier is the logic or middle tier of the application, where data is processed using business rules. The data processing tier is the data or back-end tier of the application, where data is stored and managed12

asked 02/10/2024
Zachary Janssen
39 questions

Question 48

Report Export Collapse

After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

Implement the change.
Implement the change.
Approve the test plan.
Approve the test plan.
Notify customers.
Notify customers.
Develop a rollback plan.
Develop a rollback plan.
Suggested answer: D
Explanation:

The project manager should develop a rollback plan next after determining the appropriate maintenance window in the operational infrastructure change process. A rollback plan is a contingency plan that describes how to revert to the previous state of the system or infrastructure in case of a failure or disruption during the change implementation. A rollback plan can help to minimize the impact and risk of the change and ensure business continuity and stability.

asked 02/10/2024
Tomasz Drobisz
34 questions

Question 49

Report Export Collapse

Which of the following offers administrators more direct control over operating systems?

Infrastructure as a service
Infrastructure as a service
Software as a service
Software as a service
Functions as a service
Functions as a service
Platform as a service
Platform as a service
Suggested answer: A
Explanation:

Infrastructure as a service (IaaS) offers administrators more direct control over operating systems than other cloud service models. IaaS is a type of cloud computing service that provides virtualized computing resources such as servers, storage, network, and operating systems over the internet.

IaaS allows users to rent or lease infrastructure resources on demand and pay only for what they use. IaaS gives users more flexibility and control over their infrastructure resources and enables them to configure, manage, and customize their operating systems according to their needs and preferences3

asked 02/10/2024
Szymon Strzep
45 questions

Question 50

Report Export Collapse

Which of the following items must be protected as Pll? (Select TWO).

Job title
Job title
Home address
Home address
Work phone number
Work phone number
Time zone
Time zone
Date of birth
Date of birth
Blood type
Blood type
Suggested answer: B, E
Explanation:

Home address and date of birth must be protected as personally identifiable information (PII). PII is any information that can be used to identify, contact, or locate an individual person, either alone or in combination with other sources. PII can include information such as name, email address, phone number, social security number, passport number, driver's license number, bank account number, credit card number, biometric data, medical records, etc. PII must be protected from unauthorized access, use, disclosure, modification, or destruction to prevent identity theft, fraud, or other malicious activities that may harm the individual's privacy or security.

asked 02/10/2024
Ioana Mihaila
53 questions
Total 299 questions