CompTIA PK0-005 Practice Test - Questions Answers, Page 3
List of questions
Related questions
A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:
Which of the following issues should be addressed FIRST?
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?
While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do
FIRST?
A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product.
Which of the following charts would BEST prioritize which defects to address?
Which of the following activities would a project manager perform during the closing phase? (Select
THREE).
Which of the following is a quality assurance tool?
A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?
Question