Question 1 / 40

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

Review the detailed plan.
Review the detailed plan.
Develop a preliminary scope.
Develop a preliminary scope.
Develop a transition plan.
Develop a transition plan.
Develop a project management plan.
Develop a project management plan.
Review the resource pool.
Review the resource pool.
Review the project objectives.
Review the project objectives.
Comment (0)
Suggested answer: E, F
Explanation:

Review the resource pool and review the project objectives are activities that the project manager should undertake after accepting a new project. Reviewing the resource pool involves identifying and evaluating the availability, skills, and competencies of the human and material resources that are needed for the project. Reviewing the project objectives involves understanding and clarifying the expected outcomes and benefits of the project and how they align with the organizational strategy and stakeholder expectations. These activities can help to plan and execute the project effectively and efficiently.

asked 02/10/2024