CompTIA PK0-005 Practice Test - Questions Answers, Page 7
List of questions
Related questions
A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?
A project manager has been informed that the delivery of required IT equipment will be delayed.
Which of the following is the FIRST step the project manager should take?
Which of the following BEST identifies the intent and purpose of a project closeout report?
A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:
A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).
A project implementation partner and the project manager disagree about completed requirements.
The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?
During the project initiation phase, a project team has been identified. Which of the following is the
NEXT step for the project manager?
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?
Which of the following BEST illustrates how team members with different roles should interact on the team?
For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
Question