ExamGecko
Home Home / CompTIA / PK0-005

CompTIA PK0-005 Practice Test - Questions Answers, Page 7

Question list
Search
Search

List of questions

Search

Related questions











A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

A.
Create a list of tasks and share it with the team.
A.
Create a list of tasks and share it with the team.
Answers
B.
Resend the scope of work to the team.
B.
Resend the scope of work to the team.
Answers
C.
Review the Gantt chart weekly with the team.
C.
Review the Gantt chart weekly with the team.
Answers
D.
Have the project sponsor meet with the team.
D.
Have the project sponsor meet with the team.
Answers
Suggested answer: C

Explanation:

Reviewing the Gantt chart weekly with the team would be the most effective step for the project manager to take to ensure clarity within the team after receiving feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. A Gantt chart is a graphical tool that shows the schedule of a project, including the start and end dates, durations, dependencies, milestones, and progress of each task or activity. Reviewing the Gantt chart weekly with the team can help to clarify their roles and responsibilities, assign tasks and deadlines, track and report their status and performance, identify and resolve any issues or risks, and keep them aligned and engaged with the project goals.VVVVVVVVVVVVVV

A project manager has been informed that the delivery of required IT equipment will be delayed.

Which of the following is the FIRST step the project manager should take?

A.
Make an impact assessment.
A.
Make an impact assessment.
Answers
B.
Prepare a new purchase order.
B.
Prepare a new purchase order.
Answers
C.
Select a new vendor.
C.
Select a new vendor.
Answers
D.
Create a risk register.
D.
Create a risk register.
Answers
Suggested answer: A

Explanation:

The project manager should make an impact assessment after being informed that the delivery of required IT equipment will be delayed. An impact assessment is a process of analyzing and evaluating how a change or an issue may affect the scope, schedule, cost, quality, or risks of a project. An impact assessment can help to determine the severity and implications of the delay on the project objectives and deliverables and identify any possible alternatives or corrective actions to minimize or avoid its negative effects.

Which of the following BEST identifies the intent and purpose of a project closeout report?

A.
To provide documentation of lessons learned
A.
To provide documentation of lessons learned
Answers
B.
To document variances from the initial project baseline
B.
To document variances from the initial project baseline
Answers
C.
To validate that a project has been successfully completed
C.
To validate that a project has been successfully completed
Answers
D.
To release resources and terminate all access rights
D.
To release resources and terminate all access rights
Answers
Suggested answer: C

Explanation:

To validate that a project has been successfully completed. The intent and purpose of a project closeout report is to validate that a project has been successfully completed and to summarize the goals, objectives, and outcomes of the project, as well as the lessons learned and the feedback from stakeholders. A project closeout report is a document that is submitted at the end of a project to officially conclude it and release the resources and contracts involved. It is useful for evaluating the project's success and improving the performance of future projects12

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

A.
ROI.
A.
ROI.
Answers
B.
SOW.
B.
SOW.
Answers
C.
RFI.
C.
RFI.
Answers
D.
RPR
D.
RPR
Answers
Suggested answer: A

Explanation:

The output of this exercise where the project manager is comparing the cost of the project to the cost savings the project will produce when it is complete will produce the return on investment (ROI). ROI is a financial metric that measures the profitability or efficiency of an investment by comparing its benefits or returns to its costs. ROI can help to evaluate the value or worth of a project and support decision making and prioritization. ROI is calculated by dividing the net benefits (benefits minus costs) by the total costs and multiplying by 100 to get a percentage.

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

A.
Risk report
A.
Risk report
Answers
B.
Defect log
B.
Defect log
Answers
C.
Issue log
C.
Issue log
Answers
D.
Backlog
D.
Backlog
Answers
E.
Change log
E.
Change log
Answers
F.
Progress report
F.
Progress report
Answers
Suggested answer: C, E

Explanation:

Issue log and change log are documents that should be used to record the event where the project team has just experienced an unexpected event and implemented a work-around. An issue log is a document that tracks and records any issues or problems that arise during a project and how they are resolved. An issue log can help to monitor and control the project performance and quality and prevent any negative impacts on the project objectives and deliverables. A change log is a document that tracks and records any changes or modifications that are made to the project scope, schedule, cost, quality, or resources during a project. A change log can help to document the change request, approval, implementation, and impact of each change and ensure traceability and transparency.

A project implementation partner and the project manager disagree about completed requirements.

The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

A.
SOW
A.
SOW
Answers
B.
RFI
B.
RFI
Answers
C.
RFQ
C.
RFQ
Answers
D.
WBS
D.
WBS
Answers
Suggested answer: A

Explanation:

The statement of work (SOW) would clarify what the project implementation partner was contractually expected to complete after disagreeing with the project manager about completed requirements. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.

During the project initiation phase, a project team has been identified. Which of the following is the

NEXT step for the project manager?

A.
Determine budget constraints.
A.
Determine budget constraints.
Answers
B.
Validate the business case.
B.
Validate the business case.
Answers
C.
Update the project charter.
C.
Update the project charter.
Answers
D.
Create a project schedule
D.
Create a project schedule
Answers
Suggested answer: C

Explanation:

Update the project charter. Updating the project charter would be the next step for the project manager after identifying the project team during the project initiation phase. A project charter is a document that formally authorizes a project and defines its purpose, scope, objectives, deliverables, milestones, roles and responsibilities, assumptions, constraints, risks, budget, and timeline. A project charter can help to align the expectations and interests of all stakeholders involved in a project and provide direction and guidance for planning and executing the project.

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

A.
Scope creep
A.
Scope creep
Answers
B.
Collecting requirements
B.
Collecting requirements
Answers
C.
Decision-making
C.
Decision-making
Answers
D.
Project change
D.
Project change
Answers
Suggested answer: A

Explanation:

Scope creep is most likely happening when a key stakeholder recommends to a senior developer that a new feature be added that is not part of the current requirement documentation. Scope creep is a term that refers to the uncontrolled expansion or change of a project's scope beyond its original boundaries or objectives. Scope creep can happen due to various reasons, such as changing customer demands, unclear or incomplete requirements, poor communication, lack of change control, or stakeholder interference. Scope creep can have negative impacts on a project, such as delays, cost overruns, quality issues, or reduced customer satisfaction12

Which of the following BEST illustrates how team members with different roles should interact on the team?

A.
SOW
A.
SOW
Answers
B.
WBS
B.
WBS
Answers
C.
RACI
C.
RACI
Answers
D.
PERT
D.
PERT
Answers
Suggested answer: C

Explanation:

RACI is a tool that best illustrates how team members with different roles should interact on the team. RACI is an acronym that stands for responsible, accountable, consulted, and informed. RACI is a type of responsibility assignment matrix (RAM) that defines and clarifies the roles and responsibilities of each team member for each task or activity in a project. RACI can help to improve communication, collaboration, and accountability among team members and avoid confusion, duplication, or conflicts3

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

A.
Resource plan
A.
Resource plan
Answers
B.
Organizational chart
B.
Organizational chart
Answers
C.
Project charter
C.
Project charter
Answers
D.
RACI chart
D.
RACI chart
Answers
Suggested answer: D

Explanation:

A RACI chart would be the most useful option for the project manager to illustrate roles for major project activities for an upcoming project kickoff. A RACI chart is a visual representation of a RACI matrix that shows who is responsible, accountable, consulted, and informed for each task or activity in a project using a table format. A RACI chart can help to communicate and document the roles and expectations of each team member and stakeholder for the project and ensure alignment and agreement.

Total 291 questions
Go to page: of 30