You plan the migration from a Dynamic AX 2012 to a Dynamics 365 Finance environment.

You are tasked with overseeing and planning a cutover to guarantee a smooth experience for end users during the cutover. You perform a basic data upgrade validation.

You need to perform a cutover.

Which three tasks must you perform? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

A.

Enable the Microsoft Power BI AppSource content packs for Cost management, Financial performance, and Retail channel performance.

Answers
A.

Enable the Microsoft Power BI AppSource content packs for Cost management, Financial performance, and Retail channel performance.

B.

Copy the upgraded database from the sandbox environment into the production environment.

Answers
B.

Copy the upgraded database from the sandbox environment into the production environment.

C.

Ensure that Synchronous transfer mode is enabled.

Answers
C.

Ensure that Synchronous transfer mode is enabled.

D.

Perform a smoke test.

Answers
D.

Perform a smoke test.

E.

Complete application setup tasks.

Answers
E.

Complete application setup tasks.

Suggested answer: B, D, E

Explanation:

References:

https://docs.microsoft.com/en-us/dynamics365/fin-ops-core/dev-itpro/migration-upgrade/upgrade-cutover-testing

asked 05/10/2024
Colin Ng
46 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first