A company signs a four-year contract for an IT support project. The manager wants to know how the revenue amounts will be allocated across the four-year period. You need to implement a revenue schedule to determine the revenue amounts for each month. Which setup should you use?
A.
4 years
B.
4 months
C.
60 months
D.
48 months