You are building the Bill of materials (BOM) for a new production item. The new item has a subcomponent.

Subproduction orders for the subcomponent must be created when estimating production orders.

You need to configure the BOM line to generate sub production orders.

Which BOM line type should you use?

A.

Vendor

Answers
A.

Vendor

B.

Item

Answers
B.

Item

C.

Phantom

Answers
C.

Phantom

D.

Pegged supply

Answers
D.

Pegged supply

Suggested answer: D

Explanation: