List of questions
Related questions
Question 76 - MB-335 discussion
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to It. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
* Create a purchase agreement for the subcontracting vendor and add SP-01 as the painting service.
* Create a vendor resource then create a work cell for outsourced painting and add the resource to the work cell.
* Create a production flow process activity for the painting work cell and add the component to be painted as a picking activity.
* Create a server term to tie the purchase agreement to the activity.
Does the solution meet the goal?
Yes
No
0 comments
Leave a comment first