A company produces multiple products that require an installation kit that includes 50 components.
The company does not want to include these 50 components in every Bill of materials (BOM). You have a BOW kit that includes all SO components, but you do not want it to produce a separate production order.
You need to set up the product BOM for the finished good.
What should you do?
A.
Select Phantom on the engineering fast tab on the kit item.
B.
Change the coverage group on the kit item to Manual.
C.
Change the line type to Pegged supply
D.
Change the line type to Phantom
Your answer: