A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.

The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view.

You need to configure the system to meet the requirements.

Which three options should you configure? Each answer presents a partial solution.

NOTE: Each correct selection is worth one point.

A.

Capable to Promise

Answers
A.

Capable to Promise

B.

finite capacity

Answers
B.

finite capacity

C.

bottleneck resource

Answers
C.

bottleneck resource

D.

operations scheduling

Answers
D.

operations scheduling

E.

job scheduling

Answers
E.

job scheduling

Suggested answer: B, D, E