A company uses Dynamics 365 Supply Chain Management for Process manufacturing.

You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.

You need to optimize the planned production orders.

What should you do?

A.

In Planned orders, combine the production orders.

Answers
A.

In Planned orders, combine the production orders.

B.

Firm the orders.

Answers
B.

Firm the orders.

C.

Rerun master planning. Select the dynamic plan with a coverage time fence of two weeks.

Answers
C.

Rerun master planning. Select the dynamic plan with a coverage time fence of two weeks.

D.

Rerun master planning. Select the static plan with a coverage time fence of two weeks.

Answers
D.

Rerun master planning. Select the static plan with a coverage time fence of two weeks.

Suggested answer: C