A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.

Purchase orders for a raw material are created more frequently than needed. This results in missed discounts with the vendor who sells the raw material.

The raw material items have a 30-day lead time. The company is willing to delay sales and production order demand that may consume the raw material for up to 15 days to consolidate purchase orders.

You need to configure the setup to include lead time and consolidate purchase orders.

What should you configure?

A.

negative days only

Answers
A.

negative days only

B.

positive days

Answers
B.

positive days

C.

dynamic negative days and negative days

Answers
C.

dynamic negative days and negative days

D.

dynamic negative days only

Answers
D.

dynamic negative days only

Suggested answer: C