Which two configuration steps must a VMware Cloud Foundation administrator apply to achieve north/south connectivity while setting up an edge VM node for a workload domain from the SDDC Manager user interface? (Choose two.)

A.
ToR Switches VRFs
Answers
A.
ToR Switches VRFs
B.
OSPF Configuration
Answers
B.
OSPF Configuration
C.
BGP Configuration
Answers
C.
BGP Configuration
D.
vSphere VDS Uplinks
Answers
D.
vSphere VDS Uplinks
E.
NSX VDS Uplinks
Answers
E.
NSX VDS Uplinks
Suggested answer: D, E

Explanation:

The two configuration steps that a VMware Cloud Foundation administrator must apply to achieve north/south connectivity while setting up an edge VM node for a workload domain from the SDDC Manager user interface are:

NSX VDS Uplinks

BGP Configuration

According to the web search results, the NSX VDS uplinks are required to connect the edge VM node to the physical network and provide north/south traffic for the overlay and public networks.The NSX VDS uplinks must be configured with named teaming policies that pin the traffic to specific VLANs and uplink ports1. The BGP configuration is required to enable dynamic routing between the NSX Tier-0 gateway and the physical routers.The BGP configuration must be done on both the NSX-T Data Center and the ToR switches2.