What is the correct sequence of steps to add a new VI Workload Domain in a VMware Cloud Foundation environment?

A.
1. Configure DNS. 2. Create a network pool. 3. Commission hosts. 4. Add licenses to SDDC Manager. 5. Create the workload domain.
Answers
A.
1. Configure DNS. 2. Create a network pool. 3. Commission hosts. 4. Add licenses to SDDC Manager. 5. Create the workload domain.
B.
1. Configure DNS. 2. Commission hosts. 3. Create a network pool. 4. Add licenses to SDDC Manager. 5. Create the workload domain.
Answers
B.
1. Configure DNS. 2. Commission hosts. 3. Create a network pool. 4. Add licenses to SDDC Manager. 5. Create the workload domain.
C.
1. Create a network pool. 2. Commission hosts. 3. Add licenses to SDDC Manager. 4. Create the workload domain.
Answers
C.
1. Create a network pool. 2. Commission hosts. 3. Add licenses to SDDC Manager. 4. Create the workload domain.
D.
1. Create a network pool. 2. Commission hosts. 3. Create the workload domain. 4. Add licenses to SDDC Manager.
Answers
D.
1. Create a network pool. 2. Commission hosts. 3. Create the workload domain. 4. Add licenses to SDDC Manager.
Suggested answer: A