HOTSPOT

You are supporting the go-live process for a company. The company is responsible for migrating data to the Power Platform by using a custom solution.

The company reports the following issues:

Migration processes fail due to operation timeouts.

Records that include lookup columns often fail to load.

You need to recommend a solution.

What should you recommend? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.


Question 16
Correct answer: Question 16

Explanation:

Box 1: Increase multithreading and/or batch size settings

Box 2: Ensure you are loading data in a specific order.

Load the base tables in the hierarchies first.