An engineer has been tasked with providing disaster recovery for an organization's primary Cisco FMC. What must be done on the primary and secondary Cisco FMCs to ensure that a copy of the original corporate policy is available if the primary Cisco FMC fails?

A.

Configure high-availability in both the primary and secondary Cisco FMCs

Answers
A.

Configure high-availability in both the primary and secondary Cisco FMCs

B.

Connect the primary and secondary Cisco FMC devices with Category 6 cables of not more than 10 meters in length.

Answers
B.

Connect the primary and secondary Cisco FMC devices with Category 6 cables of not more than 10 meters in length.

C.

Place the active Cisco FMC device on the same trusted management network as the standby device

Answers
C.

Place the active Cisco FMC device on the same trusted management network as the standby device

D.

Restore the primary Cisco FMC backup configuration to the secondary Cisco FMC device when the primary device fails

Answers
D.

Restore the primary Cisco FMC backup configuration to the secondary Cisco FMC device when the primary device fails

Suggested answer: D
asked 07/10/2024