An IS auditor finds that the cost of developing an application is now projected to significantly exceed the budget. Which of the following is the GREATEST risk to communicate to senior management?

A.

Noncompliance with project methodology

Answers
A.

Noncompliance with project methodology

B.

Inability to achieve expected benefits

Answers
B.

Inability to achieve expected benefits

C.

Increased staff turnover

Answers
C.

Increased staff turnover

D.

Project abandonment

Answers
D.

Project abandonment

Suggested answer: B