Which of the following findings would be of GREATEST concern when reviewing project risk management practices?

A.

There are no formal milestone sign-offs.

Answers
A.

There are no formal milestone sign-offs.

B.

Qualitative risk analyses have not been updated.

Answers
B.

Qualitative risk analyses have not been updated.

C.

Ongoing issues are not formally tracked.

Answers
C.

Ongoing issues are not formally tracked.

D.

Project management software is not being used.

Answers
D.

Project management software is not being used.

Suggested answer: C