Which of the following findings would be of GREATEST concern when reviewing project risk management practices?
A.
There are no formal milestone sign-offs.
B.
Qualitative risk analyses have not been updated.
C.
Ongoing issues are not formally tracked.
D.
Project management software is not being used.