Various teams in different organizations within an enterprise are preparing low-level design documents to capture network parameters using a Waterfall project model:
• hardware sizing and power consumption
• Layer 2 and layer 3 services parameters
• configuration of all control plane protocols
Input from relevant stakeholders was captured at the start of the project, and the project scope has been defined based on the parameters above. What impact will it have on documentation and project deliverables if the stakeholders ask to have changes carried out in the network before the information has been captured?
This provides more opportunity to think outside the box.
Rework is expected before the delivery.
Significant effort and time are required.
This provides a flexible approach to incorporate changes.