A consultant needs to evaluate project management methodologies for a new service deployment on the existing network of a customer. The customer wants to be involved in the end-to-end project progress and be provided with frequent updates. The customer also wants the ability to change the requirements if needed, as the project progresses. Which project management methodology should be used?

A.

three principles

Answers
A.

three principles

B.

phased

Answers
B.

phased

C.

Agile

Answers
C.

Agile

D.

Waterfall

Answers
D.

Waterfall

Suggested answer: C