Question 18 - C_TS462_2023 discussion
What settings should you make to ensure precise scheduling is used when the system performs delivery scheduling? Note: There are 3 correct answers to this question.
A.
Maintain the transit time in the route in hours and minutes.
B.
Assign a shift sequence to the working times.
C.
Assign a set of working times to the plant.
D.
Assign a set of working times to the shipping point.
E.
Maintain shifts defining the times for starting and ending work.
Your answer:
0 comments
Sorted by
Leave a comment first