Question 79 - C_TS4FI_2023 discussion

Report
Export

As a pre-closing activity, selected suppliers are to confirm their balances.

Which confirmation procedure do you use when a response is expected only in case of discrepancies?

A.

Balance confirmation

Answers
A.

Balance confirmation

B.

Account statement

Answers
B.

Account statement

C.

Balance request

Answers
C.

Balance request

D.

Balance notification

Answers
D.

Balance notification

Suggested answer: D