Question 79 - C_TS4FI_2023 discussion
As a pre-closing activity, selected suppliers are to confirm their balances.
Which confirmation procedure do you use when a response is expected only in case of discrepancies?
A.
Balance confirmation
B.
Account statement
C.
Balance request
D.
Balance notification
Your answer: