Please read this scenario prior to answering the question

Your role is consultant to the Lead Enterprise Architect within a multinational manufacturing company. The company has several manufacturing divisions.

The company has a mature Enterprise Architecture practice and uses the TOGAF standard as the basis of Its architecture frame work. In conjunction with the EA program, the company uses several management frameworks. Including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.

The company has defined a strategic architecture to improve ils ability to meet customer demand and improve its ability to manage its supply chain. The strategic architecture called for the consolidation of multiple applications that have been operating independently in the divisions' production facilities. The goal is to replace the functionality of the existing applications with a new application running as a single instance in the company's primary data center.

Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufactunng requirements.

The key corporate change attributes and implementation constraints have been confirmed. The gap analysis results have been consolidated and integrated, which has identified the gaps across the Business, Data. Application, and Technology domains. The requirements, dependencies and interoperability requirements needed to integrate the new application have been reviewed, consolidated, and validated. The Business Transformation Readiness Assessment started in Phase A has been completed. The risks associated with the transformation effort have been identified, classified, mitigated for, and documented. The Implementation and Migration Plan v0.1, the draft Architecture Roadmap, and the Capability Assessment deliverables have been completed.

Because of the risks posed by the complexity of the current environment. It has been determined that a phased approach is needed to implement the target architectures. The overall implementation process Is estimated to take several years.

Refer to the Scenario

You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.

Based on the TOGAF Standard. Version 9.2. which of the following is the best answer?

A.

You recommend that the Architecture Definition Document is finalized and placed under configuration control. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. An Implementation Governance Model should be produced to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be applied as changes to the architecture. The final Implementation and Migration Plan should then be generated.

Answers
A.

You recommend that the Architecture Definition Document is finalized and placed under configuration control. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. An Implementation Governance Model should be produced to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be applied as changes to the architecture. The final Implementation and Migration Plan should then be generated.

B.

You recommend an assessment is made to determine how the plan impacts the other frameworks in use In the organization. If the plan impacts them, then coordination will be required. The business value should then be assigned to each work package, and projects identified for inclusion In the plan, taking Into account available resources and prionties for the projects. The details for the plan should be gathered together and the final Implementation and Migration Plan created.

Answers
B.

You recommend an assessment is made to determine how the plan impacts the other frameworks in use In the organization. If the plan impacts them, then coordination will be required. The business value should then be assigned to each work package, and projects identified for inclusion In the plan, taking Into account available resources and prionties for the projects. The details for the plan should be gathered together and the final Implementation and Migration Plan created.

C.

You recommend that the criteria of business value rs applied to prioritize the implementation projects and project increments. This should focus on the return-on-investment criteria as signed off by the stakeholders, and the performance evaluation criteria used to monitor the progress of the architecture transformation. The Transition Architecture phases should be confirmed using an Architecture Definition Increments Table to list the projects. The lessons learned should then be documented, and the final Implementation and Migration Plan generated.

Answers
C.

You recommend that the criteria of business value rs applied to prioritize the implementation projects and project increments. This should focus on the return-on-investment criteria as signed off by the stakeholders, and the performance evaluation criteria used to monitor the progress of the architecture transformation. The Transition Architecture phases should be confirmed using an Architecture Definition Increments Table to list the projects. The lessons learned should then be documented, and the final Implementation and Migration Plan generated.

D.

You recommend that the migration planning outputs are reviewed, and recommendations are produced for the solution development. The priorities, high-level migration strategy, and resources needed should be identified for the development team. The requirements for monitoring tools, and the performance targets for the implementation should be documented. All this information should be gathered and the final Implementation and Migration Plan generated.

Answers
D.

You recommend that the migration planning outputs are reviewed, and recommendations are produced for the solution development. The priorities, high-level migration strategy, and resources needed should be identified for the development team. The requirements for monitoring tools, and the performance targets for the implementation should be documented. All this information should be gathered and the final Implementation and Migration Plan generated.

Suggested answer: C