Question 59 - 5V0-31.23 discussion
Which two prerequisites must be met before an NSX Edge cluster can be deployed through SDDC Manager in a VI Workload Domain? (Choose two.)
A.
Host overlay and Edge overlay networks must be routable
B.
vMotion and Edge overlay networks must be routable
C.
The NSX Edge nodes must be configured through an LDAP provider
D.
SSH must be enabled on the NSX Edge nodes
E.
The FQDN of the NSX Edge nodes must be resolvable through DNS