A customer needs to add an EF280 with FC into its existing Brocade fabric but the FC ports in the SANtricity System Manager are showing the FC ports as down and the LED on the FC HIC is amber.

Which three tasks does the installer need to complete to solve this problem? (Choose three.)

A.

Verify that the ports are enabled on the switch

Answers
A.

Verify that the ports are enabled on the switch

B.

Verify that the cables are plugged into the switch

Answers
B.

Verify that the cables are plugged into the switch

C.

Verify that the server HBA has the boot BIOS enabled

Answers
C.

Verify that the server HBA has the boot BIOS enabled

D.

Verify that the EF280s management port is up

Answers
D.

Verify that the EF280s management port is up

E.

Verify that the switch zone has the WWPNs for the EF280 and Server HBAs

Answers
E.

Verify that the switch zone has the WWPNs for the EF280 and Server HBAs

Suggested answer: A, B, E

Explanation:

Verify Switch Port Status:

Step: Check the status of the FC ports on the Brocade switch.

Reason: The ports need to be enabled for communication.

Check Cable Connections:

Step: Ensure that the FC cables are properly connected to the switch.

Reason: Loose or disconnected cables can cause the ports to appear down.

Verify Switch Zoning:

Step: Confirm that the WWPNs for the EF280 and server HBAs are correctly zoned in the Brocade switch.

Reason: Incorrect zoning can prevent the devices from communicating, causing the ports to appear down.

NetApp SANtricity System Manager documentation

Brocade switch configuration and zoning guides

NetApp hardware installation and best practices guides

asked 18/11/2024
Leandro Zaneratto
46 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first