Which of the following is the MAIN reason to include previously overlooked risk in a risk report?

A.

Assurance is needed that the risk dashboard is complete and comprehensive.

Answers
A.

Assurance is needed that the risk dashboard is complete and comprehensive.

B.

Overlooked or ignored risk may become relevant in the future.

Answers
B.

Overlooked or ignored risk may become relevant in the future.

C.

The risk report must contain the current state of all risk.

Answers
C.

The risk report must contain the current state of all risk.

Suggested answer: A

Explanation:

Including previously overlooked risks in a risk report ensures the dashboard's completeness and comprehensiveness. Here's an explanation:

Comprehensive Risk Management: To achieve comprehensive risk management, it's essential to consider all potential risks, including those previously overlooked. This ensures that the risk dashboard reflects the true risk landscape of the organization.

Assurance of Completeness: Adding overlooked risks provides assurance to stakeholders that the risk management process is thorough and that no significant risks are ignored. This completeness is crucial for maintaining confidence in the organization's risk management efforts.