Suggested answer: C

Explanation:

Risk Response Process Steps:

The risk response process typically involves several key steps: analyzing risk response options, prioritizing risk responses, and developing risk response plans.

Analyzing risk response options occurs earliest because it involves evaluating the various ways to address identified risks.

Step-by-Step Process:

Analyzing Risk Response Options: This is the initial step where different potential responses to the identified risks are considered. Options may include risk acceptance, avoidance, mitigation, or transfer.

Prioritizing Risk Responses: After analyzing the options, the next step is to prioritize them based on factors such as impact, likelihood, and the cost of implementation.

Developing Risk Response Plans: Finally, detailed plans are created for the prioritized risk responses, outlining the specific actions to be taken, resources required, and timelines.

Reference:

ISA 315 (Revised 2019), Anlage 5 provides a framework for understanding the components of risk management, including the evaluation and selection of appropriate risk responses.

asked 18/11/2024
Mian Mudasir Bari
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first